SPECIFICATION SUBMITTAL
369-621b 2 05.06.12
System Startup
Lighting Control System
Quantum®
Visit 1: System pre-wire inspection.
• Familiarize the electrical contractor, project manager, owner’s representative, with wiring and mounting of
system devices.
• Understand the overall project schedule.
• Review preliminary mounting locations and wiring practices for PC/Server, QS devices or shades,
dimming/switching panels, local wall controls, ceiling mount controls/sensors, interface devices, ballasts,
and Quantum® hub(s).
• Review preliminary wiring plans of devices wired to ballasts (i.e., occupancy sensor xx is wired to fixture
number xx). Ensure IR sensors are wired to ballasts on the same loop.
• Review preliminary drawings for proper hub to EcoSystem® loop wiring.
• Provide training to the appropriate parties in dipswitch overrides.
• Review preliminary Lutron® network topology (i.e., CAT5 hub interconnections and/or Lutron® PC/server).
Visit 2: System startup.
• Audit the system to ensure the Quantum® system is installed according to Lutron specifications.
• Verify/set up system PC/Server (if applicable).
• Verify proper wiring and operation of EcoSystem® loops.
• Verify Quantum® hubs and transfer system database.
• Check loads for shorts and overloads and remove bypass jumpers.
– Dimming/switching panels should be energized in bypass, fully lamped and tested prior to our arrival.
• Verify proper wiring and operation of the Quantum® controls.
• Programming the dimming/switching panels includes:
– Panel addressing.
– Verify proper wiring and operation of control link.
– Proper load types assigned as installed or as per approved submittal drawings. As installed conditions
take precedence. This may be a modular system and if load types differ from the original design
additional/different equipment may be required.
– Circuit to button assignments as per approved submittal drawings. If no button information exists prior
to start-up, programming will be done according to written instructions from end user or end users
representative, contractor, or will be based upon the Lutron provided sequence of operations, in that order
of priority.
– Program emergency function per the installation guide for the system. This may not be applicable for
every system.
• Programming the wall controls/interfaces includes:
– Control addressing
– Verify proper wiring and operation of control link
– Set up controls to function as per the approved submittal drawings. If no control functionality is included,
controls will be programmed according to written instructions from end user or end users representative,
contractor, or will be based upon the following rules:
o Motion sensors:
- In spaces with a wall control, motion sensors will be set up as a vacancy sensor (only automatically
turning off the lights) with 15-minute +/- 1-minute timeout.
- In spaces without a wall control, motion sensors will be set up as occupancy sensors (automatically
turning the lights on and off) with a 15-minute +/- 1-minute timeout.