EcoSystem Bus Supply
An EcoSystem lighting network containing more than
one ballast, module, or driver requires an EcoSystem
Bus Supply. This supply powers one or two
independent EcoSystem buses with up to 64 ballasts
or ballast modules per bus.
Features
•ProvidespowerforeitheroneortwoEcoSystem
buses, depending on model.
•Reprogramssettingsofreplacementballasts
automatically.
•Maintainsredundantmemoryofballastandmodule
programmingforbuildingsustainability.
•Acceptsuptotwonormallyopenornormallyclosed
dry contact closures per bus to allow integration with
occupancy sensors, demand response inputs, or AV
equipment.
•Acceptsonenormallyclosedemergencyinputper
supply to allow integration with building management
and/or security systems.
•EcoSystemBusmaybewiredNEC®Class1,
IECPELVorNEC®Class2.
•Buswiresarepolarityinsensitiveandtopologyfree
•Voltageinput:100–277V~50/60Hz.
•Non-volatile(EEPROM)memorystoresspecicsystem
informationfor10yearsfrompower-downtopower
restoration.
•100%performancetestedatfactory.
•AllowsprogrammingviatheEcoSystemProgrammer.
ProgrammingcanbelockedoutviaDIPswitch.
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
Front View
(CS-1Lshown)
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
Bottom View
(CS-1Lshown)
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
Top View
(CS-1Lshown)
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
Side View
Model Number Links Enclosure
CS-1L-CM 1 No
CS-1L-WM 1 Yes
CS-2L-CM 2 No
CS-2L-WM 2 Yes
Building a Model Number
CS
XL
XM
Power Provided
Code Number of Buses Powered
1 1 EcoSystem Bus
2
2IndependentEcoSystemBuses
Enclosure
Code Enclosure
C
Notshippedwithanenclosure
W
UnitpremountedinUL-listed8×8×4in
(203×203×102mm)enclosure
1
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c204.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Specifications
Regulatory Approvals
•UL,CUL,andNOMlisted
•MeetsANSIC62.41CategoryAsurgeprotection
standards up to and including 4 kV.
•LutronQualitySystemsregisteredtoISO9001.2000
•Forcommercialuse,ClassAonly
Power
•InputVoltage:100–277V~50/60Hz
•OutputVoltage:18V-250mAmaximum
NEC®Class1,IECPELVorNEC®Class2perbus
•Devicedrawslessthan0.18A.
Wiring
•PowerWiring:12–18AWG(1.0–4.0mm
2
)
•EcoSystemBus,Class2contactclosures:
12–22AWG(0.5–2.5mm
2
)
Mounting Considerations
•RequiresUL508listedenclosureperNEC
(customer-suppliedifCMmodel).
•EnclosureprovidedifWMmodelisordered.
•MountstostandardDINrail(included).
Environment
•AmbientTemperatureOperatingRange:32–104°F
(0–40°C)
•Relativehumidity:lessthan90%non-condensing
EcoSystem Lighting Network Example
•EcoSystemBusmaybewiredinaccordancewith
NEC®Class1,IECPELVorNEC®Class2practices.
•SensorsandEcoSystemBusSupplycontactclosures
mustbewiredIECPELVorNEC®Class2.
1
2
3
4
5
6
7
8
EcoSystem Bus
EcoSystem
Ballast
EcoSystem
Module
EcoSystem
Ballast
EcoSystem
Ballast
Eco-10or
Hi-lumeBallast*
IRReceiver
Occupancy
sensor
To additional
ballasts and
modules
(upto64total)
Keypad
DaylightSensor
LightingRemote
EcoSystem
Bus Supply
(CS-1Lshown)
2
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 3 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Dimensions
Measurementsareshownas:in(mm)
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
12345678
H/L H/L NN
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
Front View
Top View
Bottom View
Left-Side View
Right-Side View
1.77(45)
3.62(92)3.62(92)
3.56
(85)
3.62
(92)
3.62
(92)
3
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 4 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Mounting
CM Models
•SelectaUL508listedelectricalenclosurewith
minimumdimensions(w×h×d):8×8×4in
(203×203×102mm).
•Mountenclosureasperapplicableinstructions.
•MountDINrailhorizontallyinthecenterofthe
enclosure.
•CliptheEcoSystemBusSupplyontoDINrail(see
diagrambelow).
CS-1/2L-(CS-1Lshown)
Measurementsareshownas:in(mm)
1 2345678
H/L H/L NN
ON
E1 E1 E2 E2
BACC //Em C
ERR
EMG
BUS
STAT
V~ PWR
Knockoutsforwiring:
f
0.75(19)
MountingHoles
6(152)
8(203)
1(25),typically
8(203)
6(152)
4(102)
4(102)
WM Models
•Mountenclosureusingthefourmountingholeswithin
theenclosure(shownbelow).
4
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 5 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Wiring: Overview
Mains Wiring and Low-Voltage Separation
•TheEcoSystem® Bus Supply is designed to separate
mainswiring(NEC®Class1)andlow-voltageIECPELV
orNEC®Class2circuits
•Followappropriatelocalandnationalcodestoavoid
violating required separation guidelines
1 2345678
H/L H/L NN
ON
E1 E1 E2 E2
BACC
E1 E1 E2 E2
BAEm C
ERR
EMG
BUS
ERR
EMG
BUS
STAT
V~ PWR
CS-2L- shown
Torstbus
ballasts and
modules
To second bus
ballasts and
modules(2L
versiononly)
LineVoltageWiringArea
LowVoltageWiringArea
Ground
Hot/Live
Neutral
5
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 6 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Wiring: Overview(continued)
H/L H/L NN
Top View(CS-2L-shown)
Mains Wiring Terminal(black)
Neutral
Hot/Live
12345678
H/L H/L NN
ON
E1 E1 E2 E2
BACC
E1 E1 E2 E2
BAEm C
ERR
EMG
BUS
ERR
EMG
BUS
STAT
V~ PWR
Front View(CS-2L-shown)
Option (OPT) Switches
LED Indicator Lights:
Bus2(green)Error/Emergency
(CS-2Lonly)
Bus2(green)Status
CS-2Lonly)
Bus1(blue)Error/Emergency
Bus1(blue)Status
MainsStatus
MainsPower
E1 E1 E2 E2
BACC
E1 E1 E2 E2
BAEm C
Bottom View(CS-2L-shown)
EcoSystem Bus 1 (blue)Terminal:
E2
E1
EcoSystem Bus 2(green) Terminal(CS-2Lonly):
E1
E2
Contact Closure Bus 1 (red)Terminal:
EcoSystemBus1CCICom
EcoSystemBus1CCI1
EcoSystemBus1CCI2
EmergencyContactClosure
Contact Closure Bus 2(red) Terminal(CS-2Lonly):
EcoSystemBus2CCI2
EcoSystemBus2CCI1
EcoSystemBus2CCICom
6
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 7 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Wiring: Line Voltage (Mains)
Wiring from Distribution to Bus Supply
•SelectsourceoffeedfortheEcoSystemBusSupply
(100–277V~).
•Turnoffbreakeratdistributionpanel.
•Runhot,neutral,andgroundwiresfromdistribution
panel to the EcoSystem Bus Supply.
•TheEcoSystemBusSupplyisgroundedviaground
clipsonbottomofmodulethroughtheDINrail.Ensure
thattheenclosureandDINrailareproperlygrounded
per national and local electrical codes.
Note
:Ballasts,modules,anddriversareinemergency
(bypass)mode(lightsatfulloutput)untilpoweris
applied to the EcoSystem Bus Supply.
Emergency Feeds and the Bus Supply
•Usenormal(non-essential)poweronly.
•Whennormalpowerdropsout,theEcoSystemBus
SupplycannotpowertheEcoSystemBus.When
this occurs, ballasts, modules, and drivers go to
emergency(bypass)mode(fulllightoutputbydefault).
SeeApplicationNote#140foradditionalinformation
relatedtoemergencyfeedwiring.
1 2345678
H/L H/L NN
ON
E1 E1 E2 E2
BACC
CS-1L- shown
Ground
Hot/Live
Neutral
7
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c804.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Wiring: EcoSystem Bus
The EcoSystem Bus connects all ballasts together and
requiresaBusSupply.1Lmodelspowerone
EcoSystemBus;2Lmodelspowertwoindependent
EcoSystem buses. Each EcoSystem Bus can support
amaximumof64ballasts,modules,ordrivers.
Class1 and Class2 Wiring
•TheEcoSystemBusmaybeNEC®Class1,IECPELV
orNEC®Class2
–NEC®Class1:Low-voltagebuswiringmaybe
runwithmainsvoltagetoanyxturethebusis
controlling
–IECPELVorNEC®Class2:Low-voltagebuswiring
mustbeseparatedfromallmainsandClass1wiring
•UsingtwodifferentcolorsforE1andE2wirehelps
prevent miswires when multiple buses are present in
the same conduit
•Consultallnationalandlocalelectricalcodesfor
separation requirements
Wiring Details
•E1andE2wiresarenotpolaritysensitive
•BuslengthislimitedbythewiregaugeusedforE1
andE2asfollows:
Wire Gauge Bus Length(max)
12AWG(4.0mm
2
) 2200ft(671m)
14AWG(2.5mm
2
) 1400ft(427m)
16AWG(1.5mm
2
) 900ft(275m)
18AWG(1.0mm
2
) 570ft(175m)
1 2345678
H/L H/L NN
ON
E1 E1 E2 E2
BACC
ERR
EMG
BUS
STAT
V~ PWR
//Em C
CS-1L- shown
E1 E2
8
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 9 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Wiring: Contact Closures
ContactclosureinputsareIECPELVorNEC®Class2
circuits and cannot be run with mains wiring. Unless
otherwisespecied,thevoltagesshouldnotexceed
12–35V-. These circuits comply with the
requirementsofNFPA70,NationalElectricCode
(NEC®).Followallapplicablenationaland/orlocal
wiring regulations.
Contact Closure Bus Terminals
Terminal Unit Label Function
C COM Common
Em CCI-EMERG Emergency
A CCI-1
ContactClosure1
B CCI-2 ContactClosure2
Emergency
Forintegrationwithasecurityorrealarmsystem,
the emergency input may be used. The alarm system
musthaveanormallyclosedrelayforproper
operation.Wiringisshowntotheright.
CommonisTerminalCandEmergencyis
TerminalEmontheEcoSystemBusSupply.Ona
2-linksupply,thereisonlyoneEmergencyInput,
whichaffectsbothlinks.
EmergencymodemustbeactivatedusingOPT
switch5.Bydefaultemergencyinputsareignored
(DIPswitch5setto“ON”).Whenswitch5is“OFF”an
openconditionbetweenterminals5and6resultsin
emergency mode activation.
E1 E1 E2 E2
BACC
E1 E1 E2 E2
BAEm C
Bottom View(CS-2L-shown)
Contact Closure Bus 1 (red)Terminal:
EcoSystemBus1CCICom
EcoSystemBus1CCI1
EcoSystemBus1CCI2
EmergencyContactClosure
Contact Closure Bus 2(red) Terminal(CS-2Lonly):
EcoSystemBus2CCI2
EcoSystemBus2CCI1
EcoSystemBus2CCICom
C Em A B
C Em
NCSecurityContactor
Emergency
Input
9
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 10 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Operation: Contact Closures
Contact Closure Inputs
ContactClosureInputs(CCI)ontheBusSupplymay
beusedtointegrateaBMSsystemoroccupancy
sensorswithanEcoSystemLightingNetwork.Ona
2-linksupply,thereisonepairofCCIsforeach
EcoSystem Bus.
TherearethreemodesofCCIoperation:
•Occupancymode
•DemandResponsemode
•SceneSelectionmode
Thesemodescanbeselectedandconguredusing
theEcoSystemProgrammer.
Occupancy Mode
CCIscommandassignedgroupsonthe
correspondingbustoan“Occupied”lightleveloran
“Unoccupied”lightlevelwhenthecontactclosuresare
opened or closed.
•WhentheCCIisinthe“occupied”state,thesystem
willcommandballastsassignedtothatCCItogoto
their“occupied”level.
•WhentheCCIisinthe“unoccupied”mode,the
systemwillcommandballastsassignedtothatCCIto
gototheir“unoccupied”level.
NotethatifballastsaregroupedtobothaCCIin
Occupancymodeandanoccupancysensor,the
occupancy sensor will not sweep the group to its
unoccupiedlevelunlesstheCCIisalsounoccupied.
Demand Response Mode
Indemandresponsemode,eachCCI,whenclosed,
appliesacongurable“demandresponse”leveltothe
group.WhentheCCIisopened,thedemand
response level is cleared.
Ballasts will scale their current light level by the
demandresponselevel(e.g.,ifthedemandresponse
levelissetto25%,allballastswilldimtoalightlevel
thatis75%oftheirpreviouslevelandwillnotdim
above75%untiltheCCIisopened).
CCI-2takespriorityoverCCI-1,soifthesamegroup
ofballastsareassignedtobothCCIs,whenbothCCIs
areclosed,theballastswillscaletothelevelsetfor
CCI-2.
Scene Select Mode
WhentheCCIsareclosedandmaintainedaccording
to the table below, the corresponding scene is
selectedonallballastsonthelink.Momentarycontact
inputsmaybeusedifScene1issetto“Unaffected”.
CCI1 CCI2 Scene
Open Open 1
Closed Open 2
Open Closed 3
Closed Closed 4
SeeApplicationNote#236forfurtherinformationon
EcoSystem Bus Supply contact closure input modes.
10
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 11 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Operation: Status LEDs
LEDsontheEcoSystemBusSupplyindicatenetwork
status.ThespecicLEDs,colorandashingmethod
is detailed below.
123 4 5678
H/L H/L NN
ON
E1 E1 E2 E2
BACC
E1 E1 E2 E2
BAEm C
ERR
EMG
BUS
ERR
EMG
BUS
STAT
V~ PWR
E1 E1 E2 E2
BACC
E1 E1 E2 E2
BAEm C
H/L H/L NN
LED
Normal
Operation
Problem
Indicator
Probable
Cause
ERR/EMG Off
On
Emergency contact
closure is active
Steady
ash
Miswiredetectedon
corresponding bus
BUS
Intermittent
ashorOff
On Unitfault
STAT
Steady
ash
Off
NoMainspoweror
unitfault
On Unitfault
V~PWR On Off NoMainspower
11
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c1204.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Operation: OPT Switches
OPTswitchesareusedtoconguretheBusSupply.
The table below describes the options.
ToplaceanOPTswitchintheOFFposition,slidethe
switchtotheleft.DefaultswitchpositionisON.
123 4 5678
H/L H/L NN
ON
E1 E1 E2 E2
BACC
E1 E1 E2 E2
BAEm C
ERR
EMG
BUS
ERR
EMG
BUS
STAT
V~ PWR
E1 E1 E2 E2
BACC
E1 E1 E2 E2
BAEm C
H/L H/L NN
OPT Description
Switch
Position
Function
1
Firstbus(green)
CCI-1inputtype
ON
Normallyopen
1
(default)
OFF
Normallyclosed
2
2
Firstbus(green)
CCI-2inputtype
ON
Normallyopen
1
(default)
OFF
Normallyclosed
2
3
3
Secondbus(blue)
CCI-1inputtype
ON
Normallyopen
1
(default)
OFF
Normallyclosed
2
4
3
Secondbus(blue)
CCI-2inputtype
ON
Normallyopen
1
(default)
OFF
Normallyclosed
2
5
Emergency
disable
ON
Emergency
contact closure
input disabled
(default)
OFF
Emergency
contact closure
input enabled
6 Programming
ON
Programming
enabled via
EcoSystem
programmer
(default)
OFF
Programming
disabled via
EcoSystem
programmer
7,8 Normal/Override
7ON,8ON
Normaloperation
(default)
7ON,8OFF
Override:
Highend
7OFF,8ON
Override:
Lowend
7OFF,8OFF
Override:
Off
123 4 5678
ON
123 4 5678
ON
OPTSwitchOFF
OPTSwitchON
12
CS-1L-CM; CS-1L-WM; CS-2L-CM; CS-2L-WMEcoSystem Bus Supply
369973c 13 04.07.17
®
SPECIFICATION SUBMITTAL Page
Job Name:
Job Number:
Model Numbers:
Operation: Combining Occupancy
Sensors with CCIs
Occupancysensorswithrelayoutputscanbewiredto
thecontactclosureinputsonthebussupply.Follow
the diagram below.
Occupancysensorrelayoutputscanbenormally
openornormallyclosed.SettheOPTswitchforthe
CCItomatchthetypeofsensoroutputbeingused.
Occupancysensor
(rearview)
Relayoutput
Common
+24V-
120~
or
277V~
Bus supply
Toterminals:
C:Common
A:CCI1or
B:CCI2
PowerPack
PP-120H(for120V~)
or
PP-277H(for277V~)
Lutron,Lutron,Eco-10,Hi-lume,andEcoSystemaretrademarksof
LutronElectronicsCo.,Inc.registeredintheU.S.andothercountries.
13