This inspection checklist is provided as a courtesy to assist with your fire alarm system installation requirements
Fire Alarm System
Inspection Results:
Dedicated 120vac circuit is posted inside the panel. 72-10.6.5.2
Is panel installation accessible and compliant with 70-110.26
As-Built Drawings Received - 907.7.3
Outputs
Fire Alarm Control Room
Contact I. D. Verified - 907.6.3.2
Installation Certificate (SF-035) Received, Signed & Dated
Record of Instructions & Completion Received - 907.7.3
Alarm signals with correct address & description 907.6.3.2
Located as per approved drawings 72-10.4.1
Double action Red in Color - 72-17.15
Final Acceptance Test (continued)
Smoke Detectors & Heat Detectors
Manual Pull Stations
Tested with smoke/heat gun or per Mfg. instructions 72-14.1.1
Alarm signals w/correct address & description - 907.6.3.2
Do all initiating devices comply w/installation requirements 72-17.4.1
Do all initiating devices perform assigned functions 72-23.1.2
Main Panel
Mag locks/door holders release on all alarms 72-21.9
Smoke dampers close per alarm matrix (see drawings) 72-21.7.1
Records retention "Documents Cabinet" 72-7.7.2.1
Duct Detectors/Tamper Switches
Visual Devices
Verify decibel levels w/meter
(max 110dBA)
72-18.4.1.2
Supervisory signals w/correct address & description 907.6.3.2
Duct detector remote test switch w/LED is installed 72-17.4.6
HVAC unit shut down with duct detector activation 72-21.7
Verify battery size and labeled with month & year 72-10.6.10.1
Breaker label, red marking & lock out in elect. panel 72-10.6.5.2.3
Wiring is provided for all devices as shown on drawings 72-7.3.2
Verify Class "A" wiring with 4' separation 907.6.1.1
Wiring methods on load side of PLFA power source 70-760.130
Consult the stamped approved plans and verify the following
Inspection Results:
Operational Instructions are posted @ F/A control panel - 907.7.3
Audible Devices
Water Flow Devices
Duct detectors restoral from panel/remote switch 72-23.8.5.4.6.4
Strobe devices are correct candela per approved plans 72-18.5.1
Strobe visual synchronization 72.18.5.5.5.2
Verify proper installation & location per approved plans 72-18.5.2.2
Ensure 120vac surge suppressor is properly installed 70-708.20 (D)
Ensure Panel is properly grounded 72-10.6.5.5
Operational Instructions are posted @ F/A control panel - 907.7.3
Verify H/S over FDC activated on waterflow only 907.6.7
Signals report w/correct address & description 907.6.3.2
Activated within 45 seconds 72-17.13
Ensure panel is properly grounded 72-10.6.5.5
Inspector's Name:
Comments:
Ensure 120vac surge suppressor is properly installed 70-708.20 (D)
Verify supervision of each circuit at each end-of-line 72-14.4.1
Breaker label, red marking & lock out in elect. panel 72-10.6.5.2.3
Phone Number:
Confirm approved drawings on site 72-7.1.1
Mechanical execution of work 70-760.24
Annunciator Panel
Power Supplies
Rough-In Installation
Final Acceptance Test
Verify battery size labeled with month & year 72-10.6.10.1
Verify proper operation 72-23.1.2
Verify annunciator panels location per approved plans 72.10.4.1
Protection against physical damage 70-300.4
Verify F/A panel is digital/analog addressable - 907.1.4
Project Name:
Address:
City, State & Zip:
Prosper Fire Rescue
Fire Marshal’s Office
PO Box 307
1500 E. First Street
Prosper, Texas 75078
Phone (972) 346-9469 Fax (972) 347-3010 www.prosperfire.com