July 2016 Code of Practice for Buses Page 25 of 27
Code of Practice for Buses
Mandatory Maintenance
Procedure Part 2
Vehicle Inspections
PO BOX 1533
ADELAIDE SA 5001
MR 1090
07/16
Company / Owner
…………………………………………………………………………
Registration Number
Address
………………………………
…………………………………………………………………………………………………....
Date
.....
…..
...........
Odometer
……………………………..
km
INSPECTION SHEET NUMBER 2
To be undertaken at intervals of not more than three months or 15,000 km whichever occurs first
All inspection procedures to be carried out in accordance with the appropriate requirements of the CODE OF
PRACTICE FOR BUSES
Item
Satisfactory
Rectified
Yes ()
No ()
Date
Signed
SUSPENSION
"U" Bolts & Centre Bolts for Security & Condition
Radius Rods & Joints for Condition
Front & Rear Axle Mounts for Condition & Cracks
Springs & Shackles for Condition
Shock Absorber & Joints for Condition
Air Bag System for Condition
BRAKES
Brake Lines & Mounts for Condition
Slack Adjusters & Auto Adjusters for Operation & Condition
Brake Linings for Wear & Contamination
Air Filter for Security & Cleanliness
Air Priority System for Operation
Air or Vacuum for Correct Build Up Time
Retarder & Exhaust Brake for Operation & Control
STEERING
Steering Box for Security & Operation
Steering System for Condition & Play
Steering Wheel & Column for Play & Security
GENERAL
Engine Insulating Material for Contamination & Security
Starter Motor for Security
Tail Shafts & Guards for Condition & Security
Universal Joints & Splines for Condition
Fuel Tank & Fuel System for Security
Wheel Bearings for Adjustment
Axle Hub Seals for Leaks
Seat Belt Condition & Operation
Door Interlocks for Correct Operation (if fitted)
BODY
Body Mounts Attachments for Security & Condition
Body for Visual Structural Defects & Corrosion
Inspection Undertaken by …………………………………. Signed………………… Date …./…./……..
*This form must be kept for a period of at least one (1) year after the inspection.
FIRST SCHEDULE: PART 2