REROOF PROCEDURES
Fill out a Building Permit application. Under Project Information check other and then note in Scope of Work,
reroof home. In the subcontractor section of the permit application fill out the section under roof.
Read and follow the Reroof Checklist (attached) and include all necessary items with your permit application.
For all inspections, the Inspectors need the following on the job: manufacturer’s installation instructions, NOC,
permit card, roof plan, and product approval sheet.
The Contractor must sign the Affidavit of Compliance (attached) and have it notarized.
All reroofs will undergo an in-progress inspection and a final inspection. The purpose of the in-progress
inspection is to verify the underlayment requirements and compliance with the Hurricane Mitigation
requirements. The contractor must schedule the in-process inspection for the day the job starts so the
inspector can visit the job at the appropriate time.
If the Contractor so chooses, the in-progress inspection may be substituted with photos that certify the
requirements associated with a reroof. The Contractor must then have adequate photos to verify that the
nails are the correct nails, installed with the correct spacing and are not over driven. Also, photos that show
compliance with the other requirements listed below. If adequate photos are not taken, the Contractor may
be required to strip back shingles to verify compliance with the code. It is recommended to take a photo of
the box of nails with the label prominently displayed.
DECK NAILING – 8d nails spaced no greater than 6” o.c. with nail heads flush with deck. For 1x12 decking
material, two nails per rafter crossing. Do not over drive the nails.
DRIP EDGE – The Fl. Building Code requires drip edge to be overlapped by a minimum 3” and to be nailed at 4”
o. c.
UNDERLAYMENT – Shall be attached to a nailable deck in a grid pattern of 12” (305 mm) between the side
laps, with 6” (152 mm) spacing at the side laps.
FLASHING – Any of the recognized methods outlined in R905.2.8.2
NAILS – Take a picture of the nail box showing that they are 8d, .113 with .028 nail heads.
PHOTOS – Must be present at the final inspection along with the signed affidavit. Photos must be able to
indicate proper installation of valley lining, drip edge, deck nailing and underlayment as outlined above.
CONTRACTOR SIGNATURE_____________________________ DATE___________________
City of Groveland Building Dept., 156 S. Lake Ave., Groveland, Fl. 34736 email - permitting@groveland-fl.gov
Phone: 352-429-2141