Permit #:
Date:
Y N N/A Y N N/A
Time:
Time:
Passed Failed
Y N N/A
FDC
Testing
Statement of Compliance letter on file with the Prosper FMO
As-Built drawings on file with the Prosper FMO
Passed Failed
Contractor's Name & License #
Rev. 03-19 Subject to change
Project Name:
Address:
Wet Pipe Sprinkler System
This inspection checklist is provided as a courtesy to assist with your sprinkler suppression system installation requirements
Visual
Sprinkler placement clearance from obstructions 13-9.5.5.2
Verify sprinkler heads are free from foreign matter 13-16.2.3.1
( 200 psi for 2 hours)
Start PSI:
( No loss of pressure)
Visual
Main & cross main piping supported per 13-(Table 17.4.2.1 a)
Pipe hangers installed per section 13-17.1.1
End PSI:
Relieved pressure and the gauge returned to zero
Branch line piping supported per section 13-17.4.3
Initiation devices activated the notification devices 13-28.2.3.1.1
Has the penetration of the dry sprinkler been sealed 13-15.3.3
Inspection Results:
Verify piping sizes and layout
Verify proper pipe installed 13-16.3.1
Are dry sprinkler min. barrel lengths per 13-(Table 15.3.1 a)
Min. Temp. & Distance from heat source 13-(Table 9.4.2.5 a)
Obstructions to sprinkler discharge 13-9.5.5
Flow from ITV initiated signals within the designed times 13-28.2.3.1
Initiation of alarm activated proper notification devices 13-28.2.3.1.1
Backflow device, size, type & flow direction 13-16.9.3.3.5
If FDC serves multi-addresses, addresses must be listed 24-5.9a
Sign with 1" letters indicating what it serves 13-16.12.5.8
Comments:
Are all freeze protection methods operational SFMO 34.718
Main drain piped outside or to drain of proper size 13-16.10.4.4
Signals to F/A panel w/correct address & description 903.4
Flow of ITV initiated signals within designed times 13-28.2.3.1
Main drain test performed, recorded permanently 13-28.2.3.4.2
Inspector's Name:
Inspection Results:
Signed Aboveground Contractor Material & Test Certificate SF-041
Surge prevention of pipe exceeding 100 psi 13-9.2.2.4.4
Support of riser piping per section 13-17.4.5
Inspector's test connection clearly indicated & accessible 13-16.9.12
NFPA 25, Contractor Certificate & As-Built Drawings in cabinet
Main drain test performed, recorded permanently13-28.2.3.4.2
Minimum deflector distance below ceiling 13-9.5.4.1.1
Minimum distances from sprinklers 13-9.5.3.4
Type, temp. & spacing of sprinklers match plans 13-9.5.1
Are sprinklers in their proper orientation per 13-9.5.4.2
Verify DCVA forward flow and certification test report provided
Signals @ FACP correspond w/monitoring station signals received
Auxiliary drains clearly indicated & accessible 13-16.10.5.3
Sign @ each control valve w/portion of building served 13-16.9.12.3
Hydraulic nameplate installed at riser per section 13-28.5.1
Spare head box, sprinkler heads, wrench & label per 13-16.2.7
Riser Room
Escutcheon plates are installed per mfg. instructions 13-16.2.5
Water pressure gauges are installed properly 13-16.13
Hydrostatic Test
Pressure pumps disconnected 13-28.2.1
Confirm underground fire line finalized w/SF-042 Certification
Phone Number:
City, State & Zip:
Proper space around riser(s) for service per mfg. (3' min.) 901.4.6
Multiple risers correspond w/ fire alarm addressing 904.3
All riser trim and valves labeled per 13-28.6.1.1
Riser room door labeled & Knox box installed 509.1
Riser room hard wired for heat & emergency lighting 13-8.2.5.2.1
A Locking documents cabinet installed per Prosper Amendments
Connection 18" to 48" above finished grade 13-16.12.5.1.2
5" Stortz w/30° downturn and locking cap 13-16.12.3.1.1
FDC with the proper drip valve for drainage 13-16.12.7
Verify 5' pathway, visible & facing the fire lane 24-5.9.5.1
Prosper Fire Rescue
Fire Marshal’s Office
PO Box 307
1500 E. First Street
Prosper, Texas 75078