1
-
is
-
."
-
.
.
Electric Service Construction Roadmap
Preliminary Phase
(Status 10)
Target: 2 Weeks
Design /
Engineering Phase
(Status 20)
Target: 14 Weeks
Pre-Construction
Phase
(Status 40)
Target: 14 Weeks
Scheduling
(Status 50)
and Construction
Phase
(Status 60)
Target: 10 Weeks
Customer calls 1-800-375-7405
to apply for a new electric service
or service upgrade. Required:
Customer's billing information.
This symbol indicates a step where delays are common. Match the corresponding
number to that in the "Unforeseen Issues" document for more information.
This symbol indicates that the process cannot proceed
until the customer fulfills the requirements in that step.
A Work Request Number (WR#)
is created and reported back to
the customer. Time: 1-3 days
Customer Fulllment Rep is
assigned to the project. They call
the customer to determine needs
and send a “PES Package.”
Time: 3 days
Customer (or their designee) must provide info
requested in the PES package. Required: expected
loads, one- line diagram, site plan, CAD le and
completed Easement Information Form at a minimum.
2
1
Loads are approved and a National Grid
Design Engineer is assigned. The Design
Engineer will schedule one or more site
meetings to gather more info about your
project and discuss available options for
providing service.
Please have all key decision makers for
your project in attendance at the initial site
meeting, for example: electrical designer
or electrician, civil contractor, project
manager or developer, architect and
nancial representative.
Time: Varies, 2-3 weeks
A civil and/or manhole survey
may be conducted by National Grid.
Time: Dependent on complexity
of the job.
The electric design for the new service is
completed and approved. Time: Dependent
on complexity of the job.
3
The CIAC is calculated to determine
the customer's nancial contribution.
Time: 5 days
A Service Agreement is drafted
and sent to the customer.
Time: 2 days
If the CIAC amount is >0, an invoice
is generated and sent to the
customer. Time: 3 days
If necessary, a Grant of Easement is
drafted by National Grid and sent to
the customer. Time: up to 4 weeks
4
5
6
The Service Agreement must be
signed by the customer and returned
to National Grid, whether or not a
CIAC payment is due.
The invoice must be paid in full
before the process can proceed.
The Grant of Easement must be signed
by the customer and returned to
National Grid.
Parallel
Efforts
For jobs requiring underground construction,
customer must meet with National Grid for
approval prior to performing any civil work.
DIGSAFE MUST BE CALLED
BY CUSTOMER OR CUSTOMER’S
AGENT BEFORE DIGGING ON
PRIVATE PROPERTY!
7
All relevant permits and environmental
requirements related to the customer's
private property must be met
8
National Grid must approve any
customer-performed civil work
before the job can progress to
the next step.
9
National Grid will le all relevant
permits and petitions with the
appropriate town and state
authorities for work needed in
the public way.
National Grid will complete any
required civil work in the public way.
10
If the project requires poles to be set in
a National Grid pole set area, National
Grid sets the poles.
11
ALL NATIONAL GRID WORK IS
WEATHER PERMITTING.
The town in which the project is located
may need to approve permits and/or
petitions led by National Grid before
the project can proceed
12
If the project is located in a non-National Grid
pole set area, poles may need to be set by other
utilities, e.g., Verizon.Time: varies, up to 3
months (depends on town, number of poles, etc)
13
Customer Actions
National Grid Actions
Site preparation, such as tree trimming
and rock drilling, is performed by
National Grid and eld checks are
conducted. Time: 2 weeks
The job is scheduled and any
overhead construction (installation
of wires, etc) is completed by
National Grid as needed.
Time: 4-6 weeks
The customer's transformer is
delivered and set on a concrete
foundation.Time: 2 weeks after
the trench inspection is approved
Secondary cable is installed by the customer
after the transformer has been installed by
National Grid.
14
15
16
Primary underground constuction is completed
by National Grid. Construction may require a
"planned outage." Time to install (or "pull"
cable): 1 month
A municipal inspection must be scheduled
by the customer and approved by the city
or town wiring inspector.
National Grid energizes the new service
and installs the electric meter.
Time: up to 1 week
17
18
Other’s Actions
WR#
123
✔
✔
This symbol indicates that
the step requires an action
by the customer.
3