SECTION 1.0 – GENERAL PROJECT DATA
1.1 Required No. of sets of plans:_______
1.2 Required Cover sheet plan index
1.3 Required Code summary
1.4 Required Site plan
1.5 P NA Professional stamp and signature
1.6 P NA Fire and life-safety plan
1.7 P NA Energy code compliance forms and calculations
SECTION 2.0 – CIVIL DATA
2.1 Required Floor plan(s)
2.2 P NA Utility vault location and details
2.3 P NA Utility maintenance agreements
SECTION 3.0 – ELECTRICAL DATA
3.1 Required No. of sets of plans: _____
3.2 Required Electrical floor plan(s)
3.3 Required Electrical load calculations
3.4 Required One line diagram
3.5 Required Feeder riser diagram
3.6 Required Available fault current information
3.7 Required Panel schedule(s)
3.8 P NA Electrical site plan
3.9 P NA Fire-rated construction details
3.10 P NA Lighting plan
3.11 P NA Emergency power system and emergency lighting plan
3.12 P NA Under-slab electrical plan
3.13 Required Structural calculations for vertical and lateral loads for equipment weighing over 400 lbs
3.14 P NA Energy code compliance forms and calculations for lighting
Tri-County/City of Beaverton
Commercial Application Checklist/Electrical Only