SECTION 1.0 GENERAL PROJECT DATA
1.1 Required No. of sets of plans:_______
1.2 Required Cover sheet plan index
1.3 Required Code summary
1.4 Required Site plan
1.5 P NA Professional stamp and signature
1.6 P NA Fire and life-safety plan
SECTION 2.0 CIVIL DATA
2.1 Required Site utility plan
2.1 Required Erision-control plan
2.2 P NA Utility vault location and details
2.3 P NA Utility maintenance agreements
2.3 P NA Storm-water calculations
SECTION 3.0 PLUMBING DATA
3.1 Required Floor plan(s)
3.2 Required Piping and material schedule
3.3 Required Equipment layout plan
3.4 Required Fixture schedule
3.5 P NA Utility site plan
3.6 P NA Building cross section
3.7 P NA Riser diagram
3.8 P NA Roof plan
3.9 P NA Backflow prevention location
3.10 P NA Irrigation plan
3.11 P NA Fire-rated construction details
3.12 P NA Under-slab plumbing plan
3.13 Required Structural calculations for vertical and lateral loads for equipment weighing over 400 lbs
Tri-County/City of Beaverton
Commercial Application Checklist/Electrical Only
Plumbing Only
2.2
2.3
2.4
2.5
Erosion-control plan
SECTION 3.0 PLUMBING DATA, continued
3.14 P NA Equipment manufacturers’ catalog “cut Sheets” or specifications
3.15 P NA Water supply calculations
3.16 P NA Sanitary system calculations
3.17 P NA Irrigation demand calculations
3.18 P NA Roof drain and storm water calculations
SECTION 4.0 JURISDICTIONAL: SPECIFIC REQUIREMENTS
4.1 P NA Required______________________
This is a modified Tri-County form #2734 for use by the City of Beaverton.
Required___________________