DEVELOPMENT GUIDE CASTROVILLE, TX
53
Residential Permit Process Overview
A residential building permit is required for all new construction, additions and alterations of
single-family and two-family structures. All other types of construction, additions and alterations,
including multi-family residential projects, are required to go through the commercial building
permit process described above.
The residential building permit process is similar to the commercial building permit process.
Residential building plan review is ordinarily completed by the City’s third-party plan reviewer
within two weeks of plan submission, provided that plans are complete, and no problems arise
that might require a resubmission. Upon review and approval of the building plans and payment
of the required fee, a building permit is issued. Construction must begin within 180 days following
of the issuance of a building permit. At least one building inspection must occur during each 180-
day period following the issuance of a building permit or the work will be considered abandoned.
If the work is considered abandoned, a new permit must be issued (and new fees paid) before
work on a project can continue.
Once all final building inspections and approvals have been obtained from the City, the owner
must apply for and receive a Certificate of Occupancy before a new structure can be occupied.
The Community Development Department is your central point of contact during the building
permitting process. Contact Community Development at (830) 931-4090 to discuss building
permit requirements as they relate to your development project.
DEVELOPMENT GUIDE CASTROVILLE, TX
54
Residential Permit Process Frequently Asked Questions
Under what conditions must I apply for a residential building permit?
A residential building permit is required for all new construction, additions and alterations of
single-family, duplex or townhouse structures. All other types of construction, additions and
alterations, including multi-family residential projects, are required to go through the commercial
building permit process described above. Please contact the Community Development
Department at (830) 931-4090 to discuss building permit requirements as they relate to your
project.
What should I do before applying for a residential building permit?
Before you apply for a residential building permit, you need to determine whether the property
is zoned appropriately for the proposed residential use. A zoning map can be found on the
Community Development page of the City website at www.castrovilletx.gov, or you may contact
the Community Development Department at (830) 931-4090 to inquire about zoning issues.
Please also refer to Chapter 2 of this Guide.
What do I need to do to obtain a residential building permit?
To obtain a residential building permit, submit the required building plans, application, and fees
to the Community Development Department and follow the process set forth later in this
chapter. If the property is located in the regulatory floodplain, a Floodplain Development Permit
and Elevation Certificate will be needed to ensure that the structure is built according to the
City’s adopted standards. More information regarding floodplain development can be found in
Chapter 4 of this guide. Contact the Community Development Department at (830) 931-4090 to
discuss building permit and floodplain requirements as they relate to your project.
Do I need a permit to install, replace, alter or enlarge a residential driveway?
Yes. All new driveways for need to be reviewed by the City and require submission of a site plan
and permit application. City inspections are required prior to placing concrete or asphalt for any
new, altered, or enlarged driveways. Routine maintenance of an existing driveway does not
require a permit.
What building codes has the City of Castroville adopted?
The City of Castroville has adopted the following building codes:
2012 International Building Code
2012 International Plumbing Code
2012 International Property Maintenance Code
2014 National Electric Code
2012 International Existing Building Code
2012 Fuel and Gas Code
2012 Mechanical Code
2012 International Residential Code
2012 International Energy Conservation Code
2012 International Fire Code
DEVELOPMENT GUIDE CASTROVILLE, TX
55
Additional standards can be found in Chapter 22 of the City of Castroville Code of Ordinances
(Buildings and Building Regulation), available online at www.castrovilletx.gov.
What do I submit to the Community Development Department for a residential
building permit?
Submit at least two hard copy complete sets of building plans, one electronic set of the building
plans, and a permit application. Contact Community Development at (830) 931-4090 to discuss
building permit requirements as they relate to your project.
When will I know if I have approval to begin construction?
Provided that your application is complete, and no technical problems are identified, you should
expect the plan review process to take approximately two weeks from the date of your plan
submission. Upon building plan approval, a building permit will be issued once the applicable fees
are paid. The signed permit must be displayed on the job site throughout the building process
(until final inspections have been approved).
When can I begin construction?
You can begin construction upon your payment of fees and receipt of your approved building
permit. You must begin construction within 180 days and receive at least one inspection for each
180-day period following issuance of your permit.
How do I request an inspection?
The City utilizes a third-party contracted inspection company, Bureau Veritas, to inspect
construction projects. Inspections related to building construction (building, plumbing,
mechanical, fire protection, and/or electrical) can be requested by contacting Bureau Veritas
directly at any of the following:
Phone: (817) 335-8111 or (Toll-Free) (877) 837-8775
Fax: (817) 335-8110 or (Toll-Free) (877) 837-8859
Email: inspectionstx@us.bureauveritas.com
The request must include the following information:
Project address
Inspection type requested
Permit number
Contractor’s name and contact information
Date inspection is to be performed
Any special instructions or requests for the inspector
Inspections received by Bureau Veritas by 5:00pm Monday-Friday (excluding Holidays) will be
scheduled for the next business day following the request. Fire protection inspections usually
take longer to schedule, so you should allow for three business days for those inspection
requests to be coordinated.
DEVELOPMENT GUIDE CASTROVILLE, TX
56
What inspections will be required?
The inspections required for your construction project varies with the complexity of a job.
Ordinarily, the City of Castroville performs its construction inspections in the following order:
Electrical T-Pole
Plumbing Rough
Water Service
Yard Sewer
Form Board Survey
Gas Wrap (Underground)
Foundation
Electric Rough
Mechanical Rough
Gas Rough Piping/Test
Plumbing Top-Out
Framing
Energy Insulation
Construction Electric
Gas Final
Electrical Final
Mechanical Final
Plumbing Final
Energy Final
Customer Service Inspection
Flatwork
Building Final
You must receive a passing inspection report prior to proceeding to the next stage.
If I am not at the site at the time the inspections are made, how will I know if the
work has been approved?
An inspection report will be left onsite of the work inspected or emailed to the main permit
contact. If you receive a partial pass or failing inspection, contact the issuing inspector for
information on what work needs to be done to receive a passing inspection. After the work has
been corrected, you must schedule a reinspection.
What about add-ons and remodeling?
The process is basically the same as for new construction. The construction plans will only reflect
those portions of the structure affected. Similarly, permits may be sought for the specific type of
work being performed (for example, plumbing, electrical, or mechanical permit). The Community
Development Department at (830) 931-4090 to discuss building permit requirements as they
relate to your project.
When can I use and occupy my building?
Once all final inspections and approvals have been obtained from the City, the City will issue a
Certificate of Occupancy. Only after a Certificate of Occupancy has been issued can a building be
occupied.
Where can I find more information?
For more information on building permits, please refer to Community Development
Department’s webpage on the City’s website at www.castrovilletx.gov. Please contact the
Community Development Department at (830) 931-4090 if you have any questions concerning
the subjects discussed in this chapter.
DEVELOPMENT GUIDE CASTROVILLE, TX
57
Residential Permit Process Checklist
Procedural
Have you met all the zoning and platting requirements?
Have you met with the Community Development Department about general requirements
for the building permit(s) you are seeking?
Submittal
Submit two hard copy sets and one electronic set of building plans for review by the
Community Development Department. Be sure your plans include the following:
1. Site Plan (property lines must be based on an accurate boundary survey)
a. The site plan must indicate the size and location of new construction and
existing structures on the site with distances from the construction to
property lines, easements, existing and proposed grades, and existing
and proposed utilities to include water, wastewater, electric and gas.
2. Floor plans (must indicate room names describing their intended use, size and
type of windows and doors, cabinets and fixtures, and ceiling heights, and
indication of fire resistance separations as required)
3. Exterior elevations (must show exterior materials, proposed height above
adjacent grade, windows and doors, roof slopes, chimneys, and overhangs)
4. Structural Plans (must show, as applicable, foundation plans, wall sections and
details, floor framing, second floor framing, ceiling framing, roof framing,
headers, and beams)
a. Foundations must be designed and sealed by a Professional Engineer or
accompanied by a sealed engineer’s approval letter. The foundation
plans must indicate the address and legal description of the lot.
5. Plumbing plans (may be combined with the floor plan; must indicate location of
the building’s water, sewer, and gas piping, and fixtures, water heaters, and gas
outlets)
6. Electrical plans (may be combined with the floor plan; must indicate the location
of receptacles and other outlets, exhaust fans, smoke detectors, carbon
monoxide detectors (if applicable), light fixtures, service equipment and panels)
7. Mechanical plans (may be combined with the floor plan; must indicate
equipment details and location)
8. Certified (Signed) Energy Compliance Report
a. Most commonly, this is a ResCheck or IC3 compliance report. ResCheck
Software Program which can be downloaded or used online at:
https://www.energycodes.gov/rescheck. IC3 Compliance Reports can be
created at: http://ic3.tamu.edu/.
DEVELOPMENT GUIDE CASTROVILLE, TX
58
Upon review and approval of the building plans, obtain building permit and begin
construction within 180 days.
Call in all inspections; obtain passing inspection report prior to proceeding to each phase of
work.
Upon successful completion of construction (approval of all final inspections), obtain
Certificate of Occupancy from the City.
DEVELOPMENT GUIDE CASTROVILLE, TX
59
Residential Permit Process - Flowchart
1. Pre-development
Meeting
2. Submit building plans
and building permit
application and pay plan
review fee.
No
Project requires permit
review and approval?
Yes
Project may proceed
without permit.
3. Plan review (usually
two weeks)
4. Building plan approval
No
Submit revisions
Yes
5. Building permit fee and
applicable utility fees
paid and permit issued
6. Construciton
inspections
7. Final inspections
8. Certificate of
Occupancy issued
DEVELOPMENT GUIDE CASTROVILLE, TX
60
Residential Permit Process Forms
Continued on next pages
CITYOFCASTROVILLE
Little Alsace of Texas
Residential Construction Permit Application
Building Permit # _________________ Valuation: $__________________
Project Address: _________________________________________________ Zoning: ______________________
Project Description: New Construction | Remodel/Addition | Demolition | Accessory Building
Plumbing | Mechanical | Electrical | Lawn Irrigation
Swimming Pool/Spa | Other: ________________________________________________
Description of Work: ______________________________________________________________________________
Utilities Needed:
Water | Sewer | Electric | Gas | None
Project in Floodplain: No | Yes
If Yes, a Floodplain Development Permit is required.
A
PPLICANT
Name:
________________________________________
Contact Person: ______________________________
Address: __________________________________________________________________________________________________
Phone Number:
___________________
Fax Number:
___________________
Email:
____________________________
P
ROPERTY
O
WNER
Name:
________________________________________
Contact Person: ______________________________
Address: __________________________________________________________________________________________________
Phone Number:
___________________
Fax Number:
___________________
Email:
____________________________
Architect / Designer (if applicable)
Contact Person
Phone Number
Registration Number
Engineer
(if applicable)
Contact Person Phone Number
Engineer License Number
General Contractor
Contact Person Phone Number
Mechanical Contractor
Contact Person Phone Number Contractor License Number
Electrical Contractor
Contact Person Phone Number Contractor License Number
Plumber/Irrigator
Contact Person Phone Number Contractor License Number
City of Castroville Highway 90 Design Criteria may apply. A permit becomes null and void if work or construction authorized is not commenced within
180 days of the date of permit issuance, or if construction or work is suspended or abandoned for a period of 180 days at any time after work is
commenced. All permits require one or more inspections.
A certificate of occupancy must be issued before any building is occupied.
I hereby certify that I have read and examined this application and know the same to be true and correct. All provisions of laws and ordinances
governing this type of work will be complied with whether specified or not. No work may begin until proper permits are approved and all associated fees
have been paid.
Signature of Applicant: ___________________________________________ Date: ____________________
Phone:(830)9314090 703PARISSTREE
T
Fax:(830)9319186
CASTROVILLE,TEXAS78009
ForOne‐&TwoFamilyResidentialBuildings
click to sign
signature
click to edit
Castroville Community Phone: 830-931-4090
Development Department Fax: 830-931-9186
703 Paris St. www. castrovilletx.gov
Castroville, TX 78009 Page 1 of 1 Revised 11-16-2016
Castroville Community Development Department
Residential Construction Permit Submittal Requirements
For New One- & Two-Family Construction Projects
“One- & Two Family Buildings” means any building used as a One- or Two-Family residence only.
CONSTRUCTION DOCUMENT SUBMITTALS: Three (3) hard-copies of complete set of construction documents
are required for plan review. An Electronic Copy (in .pdf format) may be substituted for one of the required hard copies
Construction documents must be submitted along with a completed Residential Construction Permit Application.
Note: Drawings containing a label such as “not for construction”, “for pricing only”, or otherwise indicating that the plans
are not an official final set, will not be accepted for permit application
REQUIRED DRAWINGS AND DOCUMENTS: (The Castroville Community Development Department may require
additional information if necessary.)
Drawings must be drawn to scale, dimensioned and of sufficient clarity containing the following (as applicable):
1.
Site Plan
[a]
(property lines must be based on an accurate boundary survey)
2. Floor plans (must indicate room names describing their intended use, size and type of windows and doors,
cabinets and fixtures, and ceiling heights, and indication of fire resistance separations as required)
3. Exterior elevations (must show exterior materials, proposed height above adjacent grade, windows and doors, roof
slopes, chimneys, and overhangs)
4. Structural Plans (must show, as applicable, foundation plans
[b]
, wall sections and details, floor framing, second
floor framing, ceiling framing, roof framing, headers, and beams)
5. Plumbing plans (may be combined with the floor plan; must indicate location of the building’s water, sewer, and
gas piping, and fixtures, water heaters, and gas outlets)
6. Electrical plans (may be combined with the floor plan; must indicate the location of receptacles and other outlets,
exhaust fans, smoke detectors, carbon monoxide detectors (if applicable), light fixtures, service equipment and
panels)
7. Mechanical plans (may be combined with the floor plan; must indicate equipment details and location)
8. Certified (Signed) Energy Compliance Report
[c]
NOTES:
a. The property must be platted in accordance with City Ordinance before a permit will be issued. The site plan must indicate
the size and location of new construction and existing structures on the site with distances from the construction from lot
lines and existing structures, easements, existing and proposed grades, and existing and proposed utilities to include water,
wastewater, electric and gas. A Form Survey or Pier Survey indicating the location of the building in relation to all property
lines and easements that is sealed by a State of Texas Registered Professional Land Surveyor will be required to be on site for
the Plumbing Rough Inspection or Foundation inspection approval as applicable. Visit http://txls.texas.gov/education/ and
follow the instructions to search for Texas Registered Land Surveyors.
b. It is recommended that foundations be designed by a Professional Engineer. If the foundation is designed by a Professional
Engineer, the design must be in accordance with the 2012 International Residential Code, and must be sealed by the State of
Texas Licensed Engineer that designed the foundation plans, and indicate the address and legal description of the lot.
Concrete Foundation plans must show concrete specifications, slab thickness, and all dimensions, locations, and details of
beams, rebar (if applicable), post-tensioning cables (if applicable), other notes and requirements by the Engineer (if
applicable), and the address and legal description of the lot.
Pier & Beam Foundation plans must show all locations, dimensions, and spacing of piers, beams, and floor joists, details,
notes, and/or requirements by the Engineer (if applicable), and the address and legal description of the lot.
c. Most commonly, this is a ResCheck or IC3 compliance report. ResCheck Software Program which can be downloaded or
used online at: https://www.energycodes.gov/rescheck. IC3 Compliance Reports can be created at: http://ic3.tamu.edu/ Please
note that Energy Testing Reports for the required Duct Leakage Test and Blower Door Test are required to be prepared by a
3
rd
Party Energy Testing Company that is registered with the City of Castroville and be on-site prior to final inspection.
These Energy Testing Companies can also prepare the Energy Compliance Report for permit submittal.
Typical New Residential Inspections
Plumbing Rough
Water Service
Yard Sewer
Form Board Survey
Form Board Survey must be onsite
during inspection
Gas Wrap
Foundation
Electric Rough
Mechanical Rough
Gas Rough Piping/Test
Plumbing Top-Out
Framing
Energy Insulation
Construction Electric
Gas Final
Electrical Final
Mechanical Final
Plumbing Final
Energy Final
Blower door and duct leakage test
reports must be onsite during inspection
Building Final
Customer Svc. Insp. Form
T-Pole
Flatwork
Before
Insulation
Electrical Contractor
Master Electrician
Master Sign Electrician
Electrical Sign Contractor
Responsible Master Plumber
Other:
Fire Alarm Contractor
General Contractor
Fire Extinguisher Contractor
Residential: New Remodel Accessory
Fire Sprinkler Contractor
PHONE:
FAX:
PHONE:
CELL:
DATE:
TCEQ Licensed Irrigator
Commercial:
New
Remodel
Accessory
** As of 11/10/2015 Backflow Prevention Assembly Tester Contractor Registration requires a fee of $40.00
Energy Testing Contractor
ADDRESS (MAILING):
SIGNATURE:
CONTRACTOR INFORMATION
COMPANY NAME:
A/C and Refrigeration Contractor
CITY, STATE, ZIP:
CITY, STATE, ZIP:
REGISTERED AGENT:
LICENSE/REGISTRATION #:
COMPANY ADDRESS:
City of Castroville
CONTRACTOR REGISTRATION FORM
PROVIDE COPY OF DRIVER’S LICENSE, STATE LICENSE/REGISTRATION, AND LIABILITY INSURANCE
TYPE OF CONTRACTOR
MARK ALL THAT APPLY
EMAIL:
EMAIL:
Backflow Prevention Assembly Tester**
Affidavit: Homeowner Acting as Contractor
Property Information
Project Address: Permit #:
Owner Information
Owner Name(s): Contact Person:
Mailing Address:
Phone: Fax: Email:
In recent years, an increasing number of City of Castroville homeowners have accepted the Contractor
responsibilities for new construction, alterations or additions to their homes. To assist our residents in meeting
this challenge, the Community Development Department feels it is beneficial to alert our residents to some of
the responsibilities required in completing the permitted property improvement.
In order for a homeowner to act as the Contractor, the homeowner must reside in that residence and claim it as
a homestead under the laws of the state.
Homeowner(s) read and sign the following:
For matters concerning the above listed Project Address, I attest that I am the homeowner of the property, I
reside therein, and the property is my homestead. I hereby request to act as my own Contractor, and do affirm
and attest to the following:
1. I attest, as property owner, that I am performing the work that is described on the permit application and
that I will not be assisted by any other person performing any part of the work for compensation without
that person first registering with the City of Castroville. I understand that any person performing any part
of the work for compensation must hold the applicable licenses as required by the State of Texas.
2. I am responsible, as the Contractor and permit holder, for the performance of all sub- contractors and
compliance with the plans and specifications on file with the City of Castroville.
3. I will comply with all requirements of the City of Castroville’s adopted Codes and Ordinances and must
ensure that all required inspection approvals are granted by the City of Castroville prior to any use or
occupancy of any construction affected by permits issued.
4. If I, or my sub-contractors, fail to call for the required inspections, I am then responsible, at the City’s
request, for exposing all necessary areas or removal of all or part of installed work that was completed
in violation of the City of Castroville Ordinance(s).
5. The City will perform, as part of the permit fee, two compliance inspections for each construction
category (see the required inspection list available from the Community Development Department). I
further acknowledge that I am subject to a re-inspection fee for each additional inspection in accordance
with City of Castroville Ordinances.
6. All work shall be performed in accordance with City of Castroville Ordinances. Please be advised
homeowner contractors shall be held to the same standard as conventionally registered contractors.
Signature of Homeowner: Date:
CITY OF CASTROVILLE
Little Alsace of Texas
Phone: (830) 931‐4090
Fax:
(830) 931‐9186
703 PARIS STREET
CASTROVILLE,
TEXAS 78009
City of Castroville
Utilities System
1209 Fiorella St
Castroville, TX 78009
P: (830) 931-4070
F: (830) 931-6373
Page 1 of 3
Residential Utilities Application
Please complete the application fully and return to City Hall with payment.
Service Start Date:
Account #:
Service Address:
City
State:
Zip:
Mailing Address:
City
State:
Zip:
Customer’s Name:
Date of Birth:
Driver’s License# / State ID:
State
SSN:
Phone #s
Home:
Work :
Cell :
Email Address:
Applicants Employer:
Employer’s Address:
Co-Applicant’s Name:
Date of Birth:
Co-Applicant DL# / State ID:
SSN:
Co-Applicant Email Address:
Phone#:
Co-Applicant Employer:
Employer’s Address:
Type of Trash Service:
Residential
Residential
Number of Cans:
Number of Recycle Bins:
NOTE: Residential trash is picked up once a week.
New Connections Requested?
None all utilities existing
Water
Sewer
Gas
Electric Overhead
Electric Underground
For Office Use Only
Utility Fees
All new accounts require a deposit plus any associated fees. The deposit will be applied to your outstanding balance when
you close-out your account.
Deposit - Residential
$150.00
New Connection Fees
Water
$
Electric
$
Impact Fee - Water
$
Gas
$
Sewer
$
Impact Fee - Sewer
$
TOTAL
$
I certify that the above information is accurate, and I agree to comply with the City of Castroville rules and regulations
stated in the City of Castroville Code of Ordinances.
Applicant’s Signature:
Date
Co-Applicant’s Signature:
Date:
City of Castroville
Utilities System
1209 Fiorella St
Castroville, TX 78009
P: (830) 931-4070
F: (830) 931-6373
Page 2 of 3
City of Castroville Utilities Fee Schedule
Fee Type
Amount
Utility Fees
Deposit - Residential
$150.00
Deposit - Commercial
$500.00
Re-Connect Fee
$50.00
Re-Read Fee
$5.00
Temporary Utility Service Connection Fee
$50.00
Misc. Water
Edwards Aquifer Authority (EAA)
$5.17/mo./account
Pass thru (Asset by EAA)
Water Tap Fee
3/4" Meter
$1,200.00
1" Meter
$1,350.00
1 1/2" Meter
$2,100.00
2" Meter
$2500 + actual cost
3" or Larger
$3500 + actual cost
Sewer Tap Fee
4 " Sewer Tap Fee
5' and above
$1,200
Below 5'
$2,200
Below 8' priced per foot
$200
6" Sewer Tap Fee
Cost to be determined by
Public Works
Electric Service
Electric Overhead w/ existing Transformer & Pole
$650 with100 ft. included
Electric Overhead Install 30' Pole with existing Transformer
$2,100 with 100 ft. included
Electric Overhead Install 45' Pole with existing Transformer
$2,700 with 100 ft. included
Electric Overhear Install Transformer & 30' Pole & 45' Pole
$6,500 with 100 ft. included
Electric Overhead Install 15 KVA OH Transformer on existing
Pole
$2,100 with 100 ft. included
Electric Overhead Install 37.5 KVA OH Transformer on existing
Pole
$2,500 with 100 ft. included
Electric Underground (Single)
$3,000 with 100 ft. included
Electric Underground with pad mount
$6,500 with 100 ft. included
Street Light Installation
$300.00
Gas Service
$1000 + actual cost
City of Castroville
Utilities System
1209 Fiorella St
Castroville, TX 78009
P: (830) 931-4070
F: (830) 931-6373
Page 3 of 3
City of Castroville Utilities Fee Schedule
Solid Waste
Service Fee - Residential
$2.00/mo.
Service Fee - Commercial
$2.50/mo.
Household Hazardous Waste - Residential
$.82/mo.
90 Gallon Recycling Cart - Residential
$3.00/mo.
Residential Garbage Collection
1/week Garbage & 1/week Recycle Collection
$20.95
Commercial & Industrial Containerized Service
Shops $ Professional (Light) 1-90 Gal Can
$23.71
Shops $ Professional (Medium) 2-90 Gal Can
$24.97
2 Cubic Yard Container - 1/week
$68.04
2 Cubic Yard Container - 2/week
$107.28
3 Cubic Yard Container - 1/week
$75.58
3 Cubic Yard Container - 2/week
$119.08
4 Cubic Yard Container - 1/week
$93.32
4 Cubic Yard Container - 2/week
$177.53
6 Cubic Yard Container - 1/week
$134.08
6 Cubic Yard Container - 2/week
$263.79
8 Cubic Yard Container - 1/week
$177.53
8 Cubic Yard Container - 2/week
$355.05
10 Cubic Yard Container - 1/week
$208.68
10 Cubic Yard Container - 2/week
$437.24
Extra Pickups
Available on regular service days only - all containers
$93.18
Lock Fee/Casters
$25.00
Rates for Roll Off Containers:
Delivery Fee
$153.00
Rental Fee (per day)
$6.12
20 Cubic Yard Container
$392.82
30 Cubic Yard Container
$428.15
40 Cubic Yard Container
$469.20
Gas
Service Checklist
Instructions: Residential Checklist for the City of Castroville TX
Checklist:
Load Sheet (Appliance Schedule)
Scaled Site Plan (PDF)
Lot Survey
Location of Gas Meter
CAD Files (If Available)
Note: CPSEnergy Gas engineering to provide cost estimate to City facilitator.
Customer Signature
CUSTOMER LOAD INFORMATION
GAS EQUIPMENT
Pressure Required BTU
FURNACE
BOILER
COOKING
WATER HEATER
POOL\SPA HEATER
GAS LIGHTING
OTHER EQUIPMENT
TOTAL
0
click to sign
signature
click to edit