1110 WEST WASHINGTON, SUITE 280
PHOENIX, ARIZONA 85007
PHONE: 602-771-1000
WWW.AZHOUSING.GOV
CHECKLIST FOR FACTORY BUILT BUILDING INSTALLATION PLAN SUBMITTAL
Plan Submittal Requirement
Plan review application completed, and plan review fee included
2
All plans, details, and calculations stamped by an engineer registered by the state of Arizona. Designs and calculations to
comply with the 2009 ICC Codes and 2008 NEC.
Minimum one original and one copy each of all documents included
4
Included self-addressed stamped package for plan documents or other means of return delivery if unable to retrieve
plans/documents from office
5
Is unit located in a flood zone:
Yes (A) – See Checklist for Flood Plain Installation Plan Submittal
No (B) – Proceed with this checklist
A
6
Site plan approved by local zoning for setback and separation to include location of the building, occupancy type or use,
building size, and all utility lines (water, sewer, gas, electric)
7
Plumbing drawings with water, sewer, and gas lines identified from tap/meter to unit.
A.
Identify size, length, and materials for each
B.
Location of all cleanouts and grade of sewer line
C.
Fixture unit calculations for each
D.
If restroom facilities are not included in the building, note provisions on site to accommodate occupants of the
new building. Educational use to include letter from school administration indicating fixture quantities on
site and calculations insuring adequate fixtures to accommodate added occupants.
A
B
C
D
8
Electrical drawings, including the isometric one-line diagram that contain the following information:
A.
Amps at site meter or service, breaker size noted on site meter or service for the new building, and load center
amps for new building
B.
Conduit size, material and distance from existing meter or service to new building
C.
Number, size, type of conductors (AL or CU), and length of feeders
D.
Wire type (ie: THHN, XHHW…)
E.
All grounding and bonding connections including grounding rod size and length
F.
Complete details of panelboards, switchboards, and distribution centers
G.
Arc fault calculations (Compliance with the 2008 NEC Art. 110.9)
A
B
C
D
E
F
9
Foundation Systems
Description of the soil class and the soil bearing pressure
Footings designed to meet the minimum bearing pressure at the depth required (if applicable)
Complete set of drawings indicating:
A. Dimensions and details of the foundation footing (support) and anchoring
B. Complete list of materials
C. A cross-identification of how materials will be used in the appropriate view.
A
B
C
Identify supports and tie-down system
Engineering calculations provided for all load conditions including:
A. Wind loads for horizontal, uplift loads, overturning
B. Horizontal and torsional earthquake effects on foundations
A
B
Multi-wide units (if applicable) to include mate-line connection details noting type of fasteners and spacing of fasteners at
the floor and roof.