LDD108 (May 9, 2008) Revised December 11, 2019
BREVARD COUNTY PUBLIC WORKS
ENGINEERING INPSECTION FEES
SITE PLAN/SUBDIVISION/UNPAVED ROADS/RIGHT-OF-WAY CONSTRUCTION
Project Information
Project Name ___________________________________________________________________________
Site Plan/Subdivision/Unpaved Road/Right-of-Way Number ______________________________________
Applicant Name __________________________________________________________________________
Proposed Site Infrastructure Construction
Site construction costs shall include, but not be limited to, clearing, demolition, grading, paving, drainage,
lighting, landscaping, traffic control, parking, sidewalks, erosion controls, fencing, and other site
improvements as determined by the County. On site water, sewer, and reuse utility lines should not be
included in these costs.
A. Onsite Improvements
1. Minor Site Plans
Construction Costs less than $20,000 $400 $______________
Each additional phase $200 $______________
2. Site Plans
If Construction costs are less than $20,000 $400 $______________
If Construction costs are $20,001 and above, use below
2% of the cost up to $500,000 $______________
1.5% of the cost between $500,001 to $1,000,000 $______________
1% of the cost over $1,000,001 $______________
Each additional phase $300 $______________
3. Subdivisions (Onsite construction costs), Unpaved Roads and Right-of-Ways/Easements
2.5% of the cost up to $500,000 $______________
2% of the cost between $500,001 to $1,000,000 $______________
1% of the cost over $1,000,001 $______________