RIGHT-OF-WAY PERMIT REQUIREMENTS AND CONSTRUCTION GUIDELINES
Page 8 of 10
CONSTRUCTION REQUIREMENTS
1. Daily Construction Requirements:
At the end of each day during the installation and construction of the Project, Permittee shall observe the following requirements:
a. Working hours under this Permit are from 7:00AM until 7:00PM.
b. No open trenches or excavations will be allowed to exist overnight or weekend.
c. Proper safety measures must be in place during the entirety of the project.
d. Access to the Project location from the Town’s Right-of-Way shall remain clear and free of debris.
e. All traffic signs must be in place per the approved Traffic Control Plan (TPC) or removed or covered if not applicable to nightly
activities.
2. Future Line Location:
The installation of non-ferrous lines in the Right-of-Way shall require a suitable means to facilitate future line location such as,
but not limited to, metallic warning tape installed above the line and/or the installation of tracer wire per Town of Frederick
Design Standards and Construction Specifications. Such lines shall be required to extent, at minimum, to the center of the Right-
of-Way or as required by the Town Engineer.
3. Minimum Cover:
Installation shall meet all requirements of the Town of Frederick Design Standards and Construction Specifications or those of the
governing authority. All bores must be at a minimum depth of 36-inches plus the diameter of the line below the lowest point of
the Right-of-Way to avoid problems with frost heave. Culverts or storm drain pipe must have a minimum cover of 18-inches and
be constructed of reinforced concrete pipe (RCP).
4. Site Access:
The Town of Frederick has minimum standards for oil and gas access roads, including privately owned access roads. Generally
stated, the standards are that the roadways must be built such that they will drain properly and the oil and gas facilities will always
be accessible by emergency vehicles and other vehicles of similar weight.
5. Excavation:
Excavation shall consist of removal of all material necessary for the construction of the roadway section to the subgrade elevation,
line, and grade shown on the plans or as specified in the contract documents. Unacceptable material defined as any earthen
material containing vegetable or organic silt, topsoil, frozen material, trees, stumps, certain man-made deposits, or industrial
waste, sludge or landfill, or other undesirable materials will be categorized as unclassified excavation and removed from the site
and disposed of in accordance with applicable Town, State and Federal requirements.
Excavation shall be performed in a careful and orderly manner with due consideration given to protection of adjoining property,
the public and workmen. Any damage to streets, parking lots, utilities, irrigation systems, plants, trees, building or structures or
private property, or the benchmarks and construction staking due to the negligence of the Contractor, shall be repaired and
restored to its original conditions by the Contractor at his expense. Those areas that are to be saved will be clearly fenced off by
the Contractor per the owner’s instructions and it will be the Contractor’s responsibility to ensure that these areas are not
damaged during the construction process. Following completion of construction, should any of these trees, shrubs or irrigation
facilities, etc. require replacement, it shall be done at the Contractor’s expense.
All excavated material shall be stockpiled in a manner that does not endanger the work or workers and that does not obstruct
sidewalks, streets and driveways. No stockpiled materials shall be allowed on the asphalt surface or adjacent walkways. The work
shall be done in a manner that will minimize interference with traffic and/or drainage of the street. The Contractor at the end of
each day shall barricade all excavations and ditch lines, remove excess material from travel ways, and thoroughly clean all street,
alleyways and sidewalks affected by the excavation. If it becomes necessary to accomplish this, all streets, alleyways (if asphalt or
concrete) and sidewalks shall be swept or washed as required by the Engineer.
Materials encountered during excavation such as rubbish, organic, or frozen material, and any other material that is not
satisfactory for use as backfill in the opinion of the Engineer, shall be removed from the site and disposed of daily by the Contractor
at his expense. Stones, concrete or asphalt chunks larger than six-inches or frozen material shall be considered unsatisfactory
backfill and removed by the Contractor.