Page 4
2.3.2. Witness Test. For Level 1 review projects only, if the EDC does not inspect the
installation within 10 business days after the minimum notice period of 10 business days,
or by mutual agreement of the Parties, the Witness Test is deemed waived.
2.4. Metering: Revenue quality metering equipment shall be installed and tested by the EDC.
(Note: The EDC may allow interconnected operations prior to the meter installation.)
2.5. Acceptance: The EDC’s representative has signed Part 2, the Certificate of Completion,
approving the facility for energization.
3. Periodic Testing. All interconnection-related protective functions and associated batteries
shall be periodically tested at intervals specified by the manufacturer, system integrator, or
authority that has jurisdiction over the Customer-Generator Facility interconnection. Periodic test
reports or a log for inspection shall be maintained.
4. Safe Operations and Maintenance. The Customer-Generator shall be fully responsible to
operate, maintain, and repair the Customer-Generator Facility as required to ensure that the
Customer-Generator Facility complies at all times with the interconnection standards it has been
certified to meet.
5. Access. The EDC shall have access to the metering equipment and the disconnecting
means of the Customer-Generator Facility at all times. The EDC shall provide reasonable
notice to the Customer-Generator, when possible, prior to using its right of access. In an
emergency or outage situation, where there is no access to an AC disconnecting means such
as a switch or breaker, the EDC may disconnect the service to the premise.
6. Exterior AC Disconnect Switch. Based upon the EDC’s concern for the safety of its
associates and for the safety of the general public, the EDC recommends the installation of an
exterior AC disconnect switch, to be available to utility personnel at all times. If such switch is
installed outside the Customer-Generator’s premises, it should be located near the billing meter
or, in the alternative, near where the service entrance facilities enter the premises. Also if
installed, this AC disconnect switch shall have a plaque to state the existence of the generating
equipment controlled by the switch, and its location if applicable. (See sample of AC Disconnect
Switch placard.) However, New Jersey’s Net Metering regulations do not specifically require the
installation of an exterior externally operable AC disconnect switch for use in isolating the
Customer-Generator Facility.
6.1 The use of an exterior AC disconnect switch, readily-accessible to the EDC, available to
utility personnel at all times: (i) provides the EDC with a means to isolate the Customer-
Generator Facility from its main distribution panel; (ii) allows the EDC to perform testing on