CITY OF CLERMONT
CONDITIONAL USE PERMIT
FILING INSTRUCTIONS
1. Prior to submitting an application, a meeting with the Development Services Director or appointed
designee, is required. Call 352-394-4083 to schedule a meeting.
2. After meeting with the Development Services Director or appointed designee, the applicant shall
prepare and submit one set of preliminary site plans and one PDF on CD for review by the Site Review
Committee (SRC) (if required). The material can also be emailed to planning@clermontfl.org. The
preliminary site plan shall clearly depict the proposed project, showing the location and dimension of
the side, topographic features including floodplains and wetlands, all existing and proposed structures,
architectural elevations (all sides), signs, driveways, parking areas and landscaping, etc.
3. After the preliminary site plans are reviewed by the Site Review Committee (SRC), a list of review
comments will be forwarded to the applicant. The applicant will then revise the preliminary site plan,
addressing the comments from the SRC. The revised plans must be approved by the SRC prior to
submitting the Conditional Use Permit (CUP) application.
4. Upon preliminary site plan approval, the applicant will submit a complete CUP application, including
the revised preliminary site plan. The revised preliminary site plan is for purposes of the conditional
use permit only, and is not an approved site plan for construction.
5. Complete CUP applications that are submitted to and accepted by the Development Services Director
on or before the 1
st
of the month will be tentatively scheduled for public hearing the following month,
pending City Manager approval. Public hearings are scheduled for the 1
st
and 4
th
Tuesdays of the
following month for the Planning and Zoning Commission and the City Council respectively.
6. Your presence at the Public Hearings is strongly recommended. Staff will present the application, but it
is the applicant’s responsibility to make a case for their request.
*The site plan submitted with the CUP application is not the final site plan approved for construction. After
the CUP is approved by the Council, site plans and the site review application shall be submitted to the Site
Review Committee for review and approval, pursuant to Chapter 86 of the City of Clermont’s Land
Development Regulations. Construction can commence only after the final site plans have been approved
and a zoning clearance has been issued.