Environmental Protection and Growth Management Department
BUILDING CODE SERVICES DIVISION | BUILDING PERMITTING
2307 West Broward Boulevard, Suite #300 • Fort Lauderdale, Florida 33312 • 954-765-4400 • Broward.org/Building
INSPECTION PLAN
Special Inspector Statement of Intent and Inspection Plan
For Reinforced Unit Masonry Inspection
Date:
_
Street Address:
Contractor:
Permit#:
Building Official:
I shall inspect the entire "Reinforced Unit Masonry" system for this building,
including but not limited to the following:
1.
Masonry units, mortar, grout and reinforcing steel meet specifications.
2.
Dowels properly placed, with adequate lapping.
3.
Steel and columns ties in columns, pilasters, and beam elevation transitions
properly placed, lapped and tied.
4.
Masonry field work: head and bed joints, horizontal joint reinforcing
installed correctly, cells free of excessive mortar fins, walls level and plumb
within tolerances.
5.
Verify grout slump, proper consolidation of grout, and proper low or highlift
grouting procedures were followed.
6.
Correct embedment of reinforcing steel, bolt, ties etc.
7.
Compliance with ACI530/ASCE5 and commentaries; the approved plans and FBC 2122,
Reinforced Unit Masonry
8.
Verify Spot Survey and Elevation Certificate have been approved by
Broward County's Building Department prior to tie beam steel inspections.
9.
Inspection report logs will be maintained at job site for steel inspections.
10.
Citv Inspections: contractor shall call for Foundation, Slab, Column and
Beam Inspections. Spot Survey must be approved by Broward County's
Building Department prior to placing tie beam concrete.
This letter of intent to be followed up by a signed and sealed Inspection Certificate of Compliance
for the Reinforced unit masonry that attests to the above, which should be submitted to the building
inspector at the truss inspection.
Special Inspector's Signature:
(Date and Affix Special Inspector's Seal)