CIT Y OF LONG BEACH | Public Works Development Guidelines
36
3.3.1
Overview
Upon approval of the proposed
development project, an applicant
can prepare project plans and
specifications for plan check
submittals to DV (private property)
and PW (ROW). Generally speaking,
DV is responsible for plan checking
projects on-site (i.e. within the PL)
while PW is responsible for plan
checking projects within the ROW
(i.e. outside the PL). Ideally, the
plan check process for both DV and
PW improvements would happen
simultaneously in order to expedite
resolution of any concerns. These
reviews are sometimes decoupled
to allow for expedited permitting
or other reasons.
PW is responsible for plan check
within a public park unless the
project is a building. BAS is
responsible for plan check of
private parks and buildings within
public parks.
An Easement is not required
for Charter/Spectrum to install
and maintain communication
lines in the public ROW. All
installations of conduits, ducts,
tunnels, poles, pole lines, cables,
wires, vaults, traps, manholes,
appliances, attachments and
appurtenances used for the
purpose of the transmission,
transportation or conveyance of
any liquid or gaseous substance,
steam air, electrical energy, or
for communication purposes,
are Franchise Pipelines.
Permitting and Installation of
Franchise Pipelines are subject
to Long Beach Municipal Code
Chapter 15.44. To apply for
Franchise Pipeline Permits, or for
information regarding installing
communication lines in the public
ROW, please contact Roger Udabe,
(562) 570-6530, roger.udabe@
longbeach.gov.
The City provides various
permitting processes to
accommodate beneficial amenities
in the public ROW such as sidewalk
dining, parklets, benches, public
art and traffic signal cabinet art.
These permitted uses within the
public ROW may be a part of a
proposed private development
project or as a “stand alone”
improvement. Either way, PW
will circulate to the applicable
stakeholders for review and
comment.
It is important to determine
upfront if you have any work within
the ROW. BAS will want to see PW
approval ahead of submission
for BAS permitting. Common
examples include:
• Awnings, canopies or other
projections into the ROW
• Doors, gates, or other items that
swing into the ROW (not allowed)
• Staging and/or construction
fencing within the ROW
3.3.2
Pre-Plan Check Meeting
For large projects that require
over $1M in ROW improvements,
a PW pre-plan check meeting is
required. The meeting shall be
held at approximately 50-75% CD
complete. For all other projects a
pre-plan check is recommended
to ensure that the PW plan check
process is as effective as possible
but not required. This includes
projects when the following apply:
• Significant offsite improvements
• Utility tie in/relocation within the
ROW
• Changes to drainage patterns
• Temporary obstruction (more
than 30 days) of traffic (vehicles
or bicycle)
• Temporary obstruction (more
than 30 days) of pedestrian
access
• Reconfiguration of street
striping
• If there is confusion as to
whether your project is a minor
or major improvement
TIP: Bring a design phase
schedule to review feasibility
of anticipated timing
3.3.3
Determine if Minor
OR Major
There are two categories of Public
Works (PW) Permits,
• Minor improvements – This
includes work that does not
substantially change the
ROW AND does not require
engineered design. This
work shall conform to City
Standard Plans http://bit.ly/
lb-engineering-standards and
can typically, but NOT always,
be issued with same day service
during business hours at the PW
permit center.