b. Extended Detention Volume - Volume
above permanent pool that is released
slowly. (see fig. 1 and 2)
(1) Extended detention volume shall be
the runoff volume produced by a 1-
yr., 24-hr. design storm or as
computed by an approved model.
The 1-yr., 24-hr rainfall data for
Wisconsin is shown in Table 4. The
relationship of runoff to precipitation
is shown in Table 5. For curve
number determination see Chapter 2,
Natural Resources Conservation
Service, Technical Release 55
(TR-55). Use the post development
curve number.
(2) Outlet design shall allow for the
release of the extended detention
volume over a period of 24 hr. or
greater.
3. Peak Flow Control - Peak flow control
shall be designed to maintain stable
downstream conveyance systems and
comply with local ordinances or conform
with regional stormwater plans where they
are more restrictive than this standard. At a
minimum:
a. Outflow shall not exceed pre-
development peak flows for both the 2-
yr. and 10-yr., 24-hr design storms.
b. All runoff and flow calculations required
for peak flow design of this practice shall
use a hydrograph-producing method such
as TR-55.
c. When pre-development land cover is
cropland, use the runoff curve numbers in
Table 2. For all other pre-development
land covers, use runoff curve numbers
from TR - 55 assuming “good hydrologic
conditions.” For post-development
calculations use runoff curve numbers
based on actual conditions.
Table 2 - Maximum Pre-Development
Runoff Curve Numbers for Cropland Areas
4. Inflow Points – All inlets shall be designed to
prevent erosion during peak flows produced by
the 10-yr., 24-hr. design storm. Any rock rip-
rap or other channel liners shall extend a
minimum of 1.5 vertical ft. below the permanent
pool elevation.
5. Outlets –All outlet designs shall incorporate
preventive measures for ice damage, trash
accumulation, and erosion at the outfall.
6. Emergency Spillway – All basins shall have an
emergency spillway. The spillway shall be
designed to safely pass peak flows produced
by
a
100-yr., 24-hour design storm routed through
the basin without damage to the structure. The
flow routing calculations shall start at the
permanent pool elevation.
7. Freeboard – The basin design shall ensure the
top of embankment, after settling, is a minimum
of 1 vertical foot above the flow depth in the
emergency spillway required to safely pass the
routed 100-yr., 24-hr. storm.
8. Side Slopes – All interior side slopes above the
safety shelf shall be 4h:1v or flatter.
9. Bedrock – If bedrock is encountered within 2 ft.
of the bottom of the pond, special precautions
shall be taken, as needed, to minimize
movement of pollutants to groundwater.
10. Earthen Embankments - Earthen
embankments
(see fig. 2) shall be designed to address potential
risk and structural integrity issues such as
seepage and saturation. All constructed earthen
embankments shall meet the following criteria.
a. The base of the embankment shall be
stripped of all vegetation, stumps, topsoil
and other matter. Stripping shall be a
minimum of 6 in.
b. For embankments where the permanent pool
is ponded 3 ft. or more against the
embankment, there shall be a core trench or
key-way along the centerline of the
embankment up to the permanent pool
elevation. The core trench or key-way shall
be a minimum of 2 ft. deep and 8 ft. wide
with a side slope of 1:1 or flatter.
c. All embankments shall be constructed with
non-organic soils and compacted to 90%
standard proctor according to the
procedures outlined in ASTM D-698 or by
using compaction requirements of USDA
Natural Resource Conservation Service,
Wisconsin Construction Specification 3. No
tree stumps, or other organic material shall
be buried in the embankment. The
constructed embankment height shall be
increased by a minimum of 5% to account
for settling.