Additional Fees:
1. Additional inspections: $200 for the first two (2) hours (minimum), $75.00 for each additional hour or portion thereof. Request for
Temporary Certificates of Occupancies or for partial Certificates of Occupancies shall be included in this section.
2. Permits required by the International Fire Code: All permits and certificates, as required by the most currently adopted version of the
International Fire Code shall be $200.00
Exception #1: No fee for open burning permits issued by the Fire District or County Fire Mitigation Officer.
3. Construction or Installation without a Permit: When construction work has started without a permit as required by this Resolution,
all work on the job shall be halted until the required fee is paid. The responsible party may be required to pay a fee which is double
that required in items 2‐3.
4. Variance Request: Any request to go before the Appeals Board as defined in the International Fire Code for an alternative materials
or methods request shall be subject to $100.00 per request. The Appeals Board may only rule on alternate materials or methods as
outlined in the International Fire Code, the are not permitted to rule on specific or administrative items in the International Fire
Code.
Use of Fire Department Equipment: Minimum per hour, or portion thereof, per vehicle. New Fire Hydrants may be subject to a fee
of $100.00 per hydrant for testing and acceptance.
# of risers:
($100 for each additional riser)
# of devices @ $2 ea.
# of risers @ $100 ea.
# of devices:
($2 per initiating device/sprinkler head)
This section is to be completed by Fire Protection District:
Cost of Construction: Sq. Footage: Date paid: Check #:
Fee Schedule
New Construction, Addition, Remodel and Tenant Finish:
Townhomes: # of units
Fire Detection and Protection System:
Residential Fire Alarm or Sprinkler system
Commercial Applications:
Special Extinguishing Systems
(includes hood systems and FM 200 systems)
$50,000 or more
(cost of construction x .006)
$50,000 and less
($260 flat fee)
New Construction
Remodel
Addition
Tennant Finish