WATER HEATER, FURNACE OR
AC REPLACEMENT
INFORMATION
PERMIT REQUIRED
A building permit is required from any person desiring to replace the water heater, furnace or AC.
The following conditions and requirements apply:
• Allowable hours for construction within the Village are 6:30 a.m. to 8:30 p.m. daily.
• Permits are authorized on a case-by-case basis.
APPLICATION CHECKLIST
All applications for a driveway permit shall include the following items and information:
o a completed short-form permit application listing the contractor(s) performing the work;
o valid contractor registration with the Village of Sugar Grove;
o Description of the piece of equipment being replaced:
o What’s being removed and what’s being installed?
o Direct Vent?
o Gas or electric?
o Tall or short tank?
o Size in Gallons?
o A/C ton?
o How many BTU’s
o Manual J or other sizing documentation; and
o a copy of the contract with the property owner’s signature.
CONTRACTOR REGISTRATION
Any contractor engaged in or having obligation to do work where the scope of work requires a
building permit is required to be registered with the Village of Sugar Grove. If the contractor is not
currently registered with the Village, a registration application can be obtained from the Building
Division at 630.391.7220 or from the Village’s website www.sugargroveil.gov
INSPECTIONS REQUIRED
Inspections may include: a pre-pour/lay inspection and/or final depending on the scope of
construction. The owner/contractor is responsible for scheduling all required inspections. Please call
630.391.7220 to schedule the inspections. Please schedule the inspections by 3:30 PM THE DAY
BEFORE you want it.
PLAN REVIEW
Please allow 10 (ten) working days for processing.