Date:……………………………….. Permit No……………..……
TOWN OF ACTON
APPLICATION FOR PERMIT TO CONSTRUCT WITHIN A PUBLIC WAY
This application must be submitted not less than five (5) days prior to any Construction within a
public way.
Notice 24 hours in advance of any construction must be given to the Town Engineer.
1. Applicant/Licensee:_______________________________Address:_________________________________________
1A. Telephone #: Email Address: ________________________________________
2. Location of Proposed Construction:
3. Purpose of Construction:
License Category (choose one) – see Rules & Regs for details:
1- New Driveway 2 -Minor Construction 3-Major Construction 4-Public Utility 5-Winter Construction
4. Length of Cut: (feet). Width of Cut: (feet). Total Area: _________(sq.ft)
6. Width of Existing Pavement: (feet)
7. Type of Existing Roadway Surface: Type of Curb:
8. Type of Existing Sidewalk Surface: Type of Shoulder:
9. Date of Construction: From: (Expires December 15
th
; Work must commence within 90 days)
For Work involving Excavations 10. Dig Safe Number:
11. Drain Layer License #:____________________________________
12. Land Disturbance Threshold certification. The proposed construction (check all that apply):
Disturbs less than 1 acre of total area
Disturbs less than 5,000 sq.ft of 1) impervious area and 2) areas with a 10% slope or greater
Does not alter an existing stormwater drainage system serving 5,000 sq.ft of impervious area
I, the undersigned herby declare that I have Read and Agree to the Town of Acton Specifications for Regulating Construction
with Public Ways dated January 22, 2018. I have deposited the required bond with the Town of Acton and I covenant and agree that
the Town may deduct from this amount the cost of repairs to the road surface, curbs, shoulders, walls or other features within the right-
of-way including replacing bounds if not completed by me to the satisfaction of the Town Engineer within the specified time.
Signature of Applicant.
Special Instructions (Internal Use):
Year Paved:_______ Pavement PCI:________ Infrared Required? (yes/no):________
Current UC:_______ LCMC Fee:_________($) Moratorium Fee:_________($)
In Sewer District? (yes/no):______ Other Instructions:
Permit issued: Date…………..……………………………………….By:………………………………………………….
Application Denied: Date…………………………………………….By:………………………………………………….