Sussex County Engineering
PLAN SUBMISSION FORM
Date: Project Name:
Project Description:
Location:
Number of Building Lots/Units for Roads:
District: Map: Parcel:
Review Fee Amount: (Roads) $ (Sanitary Sewer and/or Water) $
Separate check for Roads and Sew
er is required
Checks are made out to “Sussex County Council”
Planning & Zoning Development Appr
oval:
Subdivision No.:
RPC, Change of Zone Or
dinance No.: Approval Date:
Condi
tional Use Ordinance No.: Approval Dat
e:
Commercial Site Plan: Approval Date:
Zonin
g Designation: ie; AR-1, MR, HR
Ownership:
Sewer: Pub
lic Private
Private Water: Public
Roads: Public Private
Developer’s Name:
Contact Name:
Address:
City:
ZIP Code:
Phone Number:
State:
Design Firm:
Contact Name: Email Address:
Addres
s:
Contact Phone Number:
Please be advised, for all devel
opments with onsite community sanitary sewer treatment and disposal
systems, a copy of the DNREC Permit verifying capacity for the number of units proposed will be required.
Other:
Email Address:
Page 1
Revised 07/30/2019
PLAN REVIEW FEE SCHEDULE
FEES BASED ON THE FIRST TWO REVIEWS OF PLANS SUBMITTED
CHAPTER 99 SUBDIVISION
1. FLAT FEE $2,500.00
2. PER UNIT FEE $4
5.00 EA
CHAPTER 110
SEWER AND WATER
SEWER
1. FLAT FEE $2,000.0
0
2. PER UNIT FEE $20.00 EA
3. COUNTY PUMPING STATION AND FORCE MAIN REVIEW* $2,500.00 EA
*County will not review private pump station and force main
WATER SUSSEX COUNTY WATER DISTRICTS ONLY
1. FLAT FEE $1,500.
00
2. PER UNIT FEE $10.00 EA
ADDITIONAL REVIEWS AFTER THE FIRST TWO REVIEWS COMPLETED:
THIRD REVIEW 6
0% ORIGINAL PLAN REVIEW FEE
FOURTH REVIEW 5
0% ORIGINAL PLAN REVIEW FEE
FIFTH REVI
EW 40% ORIGINAL PLAN REVIEW FEE
PLAN REVISIONS
There will
be a fee of $1,000.00 for each revision after County’s approval of the plans for Chapter 99 (roads)
and/or Chapter 110 (sewer and water).
If plans are redes
igned, plans will be charged with original submission review fees.
Adopted Jul
y 1, 2019
Page 2
Revised 07/30/2019
CONSTRUCTION PLAN REQUIREMENTS
Construction plan sets shall include, but are not limited to, the following:
General
A total of two (2) complete sets of plans are to be submitted.
A Phase Identification Plan.
A plan Cover / Title Sheet with an index of the sheets included in the plans.
A sheet index, if applicable.
Preliminary Site Plan or Record Plat approval letter, if applicable.
Conditional Use Ordinance with conditions and stipulations, if applicable.
Change of Zone Ordinance with conditions and stipulations, if applicable.
A copy of the approved preliminary Site Plan, Master Plan or Record Plat stamped, signed and
dated by Planning and Zoning in each set of the design plans, if applicable.
Chapter 110
An approved Sewer System Concept Evaluation.
Sanitary Sewer and/or Central Water System Plans, Profiles, Details and Specifications.
Chapter 99
Private Road Construction Plans, Profiles, and Details. Include details for all structures related to
regulated improvements such as but not limited to; bridges, retaining walls, etc.
Include within the construction plans, improvements required by the Planning and Zoning
Commission or Sussex County Council approvals; i.e. sidewalks, streetlighting, and landscaping.
Bulk Grading and/or Detailed Grading Plan.*
The DelDOT Entrance Plan.
The State Fire Marshall’s Office Plan.
The Stormwater Management Plan and the Erosion and Sediment Control Plan with one (1) copy of the
Stormwater Management Report and calculations.
Other Utility Plans including but not limited to; Water, Gas, etc.
*Bulk grading plan is required during the initial submittal, while the detailed grading will be required
before bonding.
Page 3
Revised 07/30/2019