Grounding the DC side of the inverter:
A minimum #8 copper Grounding Electrode conductor must be run un-spliced from the factory identified
system grounding terminal of the inverter to the grounding electrode system of the house. The grounding
electrode system may consist of one or more of the following: Ground rod(s), Ufer ground, or metallic water
pipe with a minimum of 10 feet in the ground. (
Section 690.47)
AC wiring information:
15. The inverter shall be listed and labeled by a recognized testing agency and be identified as “Uti lity
interactive”. Ground fault protection (GFP) shall comply with
Section 690.5
2010 CEC.
Specify inverter: Make ________________ Model # __________ Elec rating _______ kW
16. Per
Section 690.9
2013 CEC, each inverter shall be protected by an overcurrent device on the AC output side
of the inverter. This can be a fuse or a circuit breaker. To correctly size the overcurrent device, locate the
maximum AC output of the inverter (in amps) on the inverter nameplate, and multiply by 1.25 (This is
required because the unit will be in continuous use for more than three hours).
Maximum AC output current____
x
1.25 =____Amps.
(This number will also be used to size the
inverter output circuit conductors.)
Where the “Maximum AC output” is shown only in Watts, divide that number by 240 and then multipl y by
1.25 to get the correct size breaker or fuse.
If the maximum AC output is between standard breaker or fuse sizes, the next higher size can be used so long
as the inverter output conductors are sized sufficiently large enough for the amount of current produced by
the inverter.
Important note:
Where a fused disconnect switch is installed, the output conductors from the
inverter will connect to the
“LOAD”
side (
bottom
) terminals of the switch and the wiring from the utility will
connect to the
“LINE”
side (
top
) terminals. This meets the requirement of
Section 404.6(C)
and will reduce
the risk of electrical shock hazards when changing a fuse with the system still energized by the utility
electrical supply.
17. Many utility providers require a performance meter and a safety disconnect switch to be installed between
the PV power source and their equipment. This means that the AC power output from the inverter(s) may not
connect directly into the electrical panel of the house. For a single inverter, the output from the inverter
disconnect switch will connect to the performance meter (if required). Where multiple central inverters are
installed, they will usually go first to a solar load center. This is just a standard circuit breaker panel that
collects together the output circuits from the individual inverters. Each inverter will have its own circuit breaker.
The size of each circuit breaker will be determined from step #16. From this panel one feeder will go to the
performance meter, then to the safety disconnect switch and lastly to the point of interconnection at the
house electrical panel. No electrical loads shall be connected between the output of the inverter and the
connection to the house electrical panel. Contact your local utilities for performance meter and AC utility
disconnect switch requirements.
18. Where a performance meter is required by the local utility to record the power produced by the PV system, the
output wiring from the inverter shall always connect to the
“LINE”
side terminals of the meter.
19. Where disconnect switches (with or without fuses) are installed in the circuit from the inverter output terminals
to the house electrical panel, the wiring originating at the inverter(s) shall always connect to the
“LOAD”
side terminals of
ANY
disconnect that has been installed
20. The connection to the breaker panel
shall
be through a dedicated circuit breaker that connects to the panel
bus bars in an approved manner. “Load Side Taps” where the inverter AC wiring does not terminate using a
dedicated breaker or set of fuses are prohibited under
ANY
condition by
Section 705.12
.
21. Per Section 690.64(B)(2), the sum of all overcurrent protective devices supplying power to the busbar or
conductor shall not exceed 120% of their rating. In most PV installations, the breakers feeding the busbar
are the main breaker and the backfed PV breaker. Per Section 690.64(B)(7), to utilize the 120% rule, the
PV backfed breaker must be at the opposite end of the main breaker location. For a 100 amp rated bus,
this means that the main breaker and the PV backfed breaker shall not add up to more than 120 amps. For
a 200 amp rated bus, the combined ampacity of the two breakers (the main breaker and the PV breaker)
shall not exceed 240 amps and so on. The location of the PV backfed breaker must be identified per
690.64(B)(7) with the following verbiage:
“WARNING INVERTER OUTPUT CONNECTION. DO NOT
RELOCATE THE OVERCURRENT DEVICE.”