PERMIT PACKAGE DROP OFF CHECKLIST FOR ePlan
Application Number: ______________________ Drop Off Date: ______________________
Received by
County / Initial
Complete a Request for a Permit Application Number in BPOnline
Signed and completed this Drop Off Checklist Form
Required Forms for All Permit Packages at time of Drop Off:
Received by
County / Initial
Permit Application Form, Additional Information Form, or Revision Form
Property Appraiser’s print out with legal description
Signature Acknowledgement Form and/or Limited Power of Attorney Form
Possible Additional Forms may be required prior to Permit Payment:
(These can be uploaded whenever you have a task in your queue along with any other outstanding submittals)
Received by
County / Initial
Historical / Archaeological Form if breaking ground in any way
Asbestos Notification Form as applicable
Utility letter Water & Sewer, if new construction and other than Seminole County Utilities
Fence Estoppel letter required for all fence permits
Shed Estoppel letter may be required prior to permit issuance pending Zoning Review
Arbor Application if applicable. For arbor questions please call 407-665-7371
Recorded copy of Notice of Commencement
Owner Authorization if applicable (Landlord/Tenant Affidavit / Notarized Letter / Lease)
Plans Required at time of DROP OFF (if applicable for scope of work):
Received by
County / Initial
Site Plan
Construction Drawings (drawings requiring signing sealing must be wet or raised seal)
Product Approval form as applicable
Gas Plan Worksheet as applicable
Pool Safety Affirmation letter
If uploaded by ePlan Applicant, the following files can be uploaded as individual multi-
page files (documents requiring signing sealing must be wet or raised seal)
Energy Calculations as applicable
Truss Package as applicable
See reverse side of this page for required Drop-Off acknowledgements
Application Number: ______________________ Drop Off Date: ______________________
By signing this form I acknowledge the following:
The completeness of the documents being dropped off is not determined until the ePlan
Prescreening process takes place by a Seminole County Permit Technician. (You will
receive an email notification once all documents and/or plans have been uploaded into
the ePlan system notifying you to complete your Applicant Upload task).
I will be charged $5 per page for Seminole County Building Division to upload these
documents into ePlan.
I will be notified by the Building Division of any possible remaining required
documentation just prior to permit issuance.
I acknowledge that a deposit may be required based on the scope of work.
I also understand that when my files are uploaded by Seminole County Building Division,
there will be tasks I am responsible to complete in the ePlan system.
SEPTIC SPECIAL ACKNOWLEDGEMENT: If property is on Septic: you acknowledge that
you will be required to provide a Septic Permit or Letter of No Action prior to permit issuance.
____________________________ _____________________________________
Printed Name Signature of Applicant or Limited Power of Attorney