Construction Management Plan: 185 N Glenwood Street, Jackson, WY 83001
Project Scope:
The Glenwood Gill project will finish development of the partially built parking structure at the intersection
of Glenwood and Gill, occupying Lots 1-4 of Block 6 for Phase 1 and potential development of lots 5-6 for
Phase 2. Phase 1 construction will consist of demolition of the cabin and one-story building on lots 5-6 and
complete the existing underground parking structure while adding 20 condominium units on top of the
parking structure. The potential Phase 2 will consist of demolishing the two two-story buildings on lots 5-6
and adding an underground parking structure there tied to the Phase 1 garage on lots 1-4, with an additional
9 condominium units. Demolition of the two two-story buildings may take place during Phase 1
construction, but is to be determined based on the owner’s on-going effort to preserve these two buildings.
The estimated start of construction activities is May 2020 with an anticipated project duration of 16 months,
finishing up in September 2021. This construction management and staging plan will cover only Phase 1 of
the project. A separate, updated plan will be submitted if Phase 2 comes to fruition.
Public Impact:
Shaw will coordinate with Town of Jackson (TOJ) to develop a distribution list of neighbors that may be
affected by construction activities, including the TOJ Engineering Division. Shaw will work to minimize any
effect on adjacent properties by maintaining proactive communication including giving a minimum 48-hour
notice of any closures and after-hours work. Shaw acknowledges that the right-of-way (R.O.W.) is a shared
public use area and will coordinate with TOJ and neighbors for special event planning and construction
activities that will encroach on the R.O.W.. Along Glenwood and Gill Streets, pedestrian traffic will be
rerouted to opposite side of street with temporary signage at intersections and property boundaries. The
inconvenience to pedestrian traffic will be minimal as these areas already lack proper sidewalks.
Site Logistics & General Staging Plan:
Site logistics and the associated plans are separated into Phase 1 and Phase 2, only Phase 1 is included with
this submission. Phase 1 covers modifications to existing foundation and new construction on the northern
two thirds of the site (Lots 1-4, Block 6). Phase 1 will follow the abatement and demolition of the existing
structures on Lots 5-6 and those lots will be used as a staging area during Phase 1. This Phase 1 staging area
will house Shaw’s job office trailer, material laydown, dumpsters, temporary toilets, and limited worker
parking. The existing parking garage will house additional limited parking and material storage during Phase
1. Phase 2 will start with excavation of the new foundation on southern third of the site (Lots 5-6, Block 6)
and continue through end of the project. Throughout the project an off-site laydown and worker parking
area will be rented by Shaw. This laydown and parking area will be the lot at 345-375 N. Cache currently used
for Shaw worker parking on Hidden Hollow. Construction work hours, unless by special exception, will be
Monday-Friday 7AM-7PM and 8AM-5PM during weekends and holidays.