10 of 29
Contractor
initials
Owner
initials
Clause 8
Completion of work
The work will be complete when the contractor has nished the work in
accordance with the contract documents and any variations, there are no
omissions or defects that prevent the work from being reasonably capable
of being used for its intended purpose, any damage of the kind referred to in
Clause 19 has been repaired, and all rubbish and surplus material has been
removed from the site.
When the contractor believes the work is complete, the contractor must
notify the owner in writing certifying that the work has been completed in
accordance with this contract. Within 10 business days of receipt of written
notice from the contractor, the owner must advise the contractor in writing
of any items of work the owner considers to be incomplete or defective. If
the owner does not so notify the contractor, the work will be taken to be
complete.
The contractor must complete any outstanding work promptly and again notify
the owner in writing. Unless the owner noties the contractor in writing that
any item is still incomplete or defective within a further 10 business days from
receipt of notication by the contractor, the work will be taken to be complete.
Should there be any dispute between the parties as to whether the work
has been completed, it must be dealt with in accordance with the dispute
resolution procedure (Clause 27).
Clause 9
Statutory warranties
The contractor warrants that:
(a) the work will be done with due care and skill and in accordance with the
plans and specics set out in the contract
(b) all materials supplied by the contractor will be good and suitable for the
purpose for which they are used and, unless otherwise stated in the
contract, those materials will be new
(c) the work will be done in accordance with, and will comply with, the Home
Building Act or any other law
(d) the work will be done with due diligence and within the time stipulated in
the contract, or if no time is stipulated, within a reasonable time
(e) if the work consists of the construction of a dwelling, the making of
alterations or additions to a dwelling or the repairing, renovation,
decoration or protective treatment of a dwelling, the work will result, to
the extent of the work conducted, in a dwelling that is reasonably for
occupation as a dwelling
(f) the work and any materials used in doing the work will be reasonably t
for the specic purpose or result, if the owner expressly makes known
to the contractor or another person with express or apparent authority to
enter into or vary contractual arrangements on behalf of the contractor,
the particular purpose for which the work is required or the result that the
owner desires the work to achieve, so as to show that the owner relies on
the contractor’s skill and judgment.
These warranties do not in any way reduce or limit the contractor’s
obligations in relation to workmanship, materials, completion or other matters
specied in Clauses 2 and 3 or elsewhere in this contract. No provision of
this contract can reduce, restrict or remove these statutory warranties.
Explanation: Should any
defects or omissions become
apparent after completion, refer
to the Defects Rectication
clause (Clause 23).
Paragraph (f) on this page
relates to work where the owner
makes known to the contractor
the intended purpose of the works
or the result the owner expects
to achieve with the work. This
warranty requires the contractor to
use appropriate expertise to provide
the stated and expected results.
Explanation: Under the Home
Building Act 1989 the contractor is
required to give the warranties set
out in this clause.
The statutory warranties in the
contract are as printed in the
Home Building Act. They require
the contractor to provide a product
as agreed, in a suitable state, t for
its intended purpose, complying
with all relevant laws and within the
agreed time, or if not agreed a time
that is reasonable
Note: Any legal action for
a breach of statutory warranties
must be taken before the end of
the warranty period for the breach
ie. 6 years for a breach resulting
in a major defect (as dened in
the Home Building Act 1989) or
2 years in any other case.
The warranty period starts on
completion of the relevant work to
which it relates (but this does not
prevent proceedings from being
commenced before completion of
the work). However, if the work is
not completed, the warranty period
starts on:
(i) the date the contract is
terminated, or
(ii) if the contract is not terminated
– the date on which work under
the contract ceased, or
(iii) if the contract is not terminated
and work under the contract
was not commenced – the date
of the contract.
Other than in the case of non-
completion of work, if the breach
of warranty becomes apparent
within the last 6 months of the
warranty period, proceedings
may be commenced within a
further 6 months after the end
of the warranty period. A breach
becomes apparent when the owner
of the property becomes aware
(or ought reasonably to have
become aware) of the breach