1. Quality of construction
All work done under this contract will comply with:
1. (a) the Building Code of Australia to the extent required under the Environmental
Planning and Assessment Act 1979 (including any instrument made under
that Act)
(b)allotherrelevantcodes,standardsandspecicationsthattheworkis
required to comply with under any law
(c) the conditions of any relevant development consent or complying
developmentcerticateandanyconstructioncerticate.
2. This contract may limit the liability of the contractor for a failure to comply with (1)
if the failure relates solely to:
(a)adesignorspecicationpreparedbyoronbehalfoftheowner
(but not by or on behalf of the contractor), or
(b)adesignorspecicationrequiredbytheowner,ifthecontractorhasadvisedthe
ownerinwritingthatthedesignorspecicationcontravenes(1).
2. Payment by owner
The Contract Price includes all matters (including GST) that could be reasonably
expected to be necessary for the completion of the work. The work will be complete
whenitisnishedinaccordancewiththiscontract(exceptforanyomissionsor
defects that do not prevent the work from being reasonably capable of being used
for its intended purpose), any damage caused by the contractor is repaired and all
rubbish and surplus material are removed from the site. The owner must pay the
amount due on satisfactory completion of the work, or each stage of the work if
applicable, within 5 business days of receipt of written notice from the contractor.
3. Time for completion
The contractor must complete the work within the Completion Period which runs
from the date of this contract or, if any approval for the work is to be obtained, from
thedateofwrittennoticationofthatapprovalwhicheverislater.Thecontractorwill
be entitled to a reasonable extension of time in the event of delays to the work where
the cause of the delay is beyond the contractor’s control including but not limited
to, inclement weather, industrial disputes or variations to the work. The contractor
must take all reasonable steps to minimise any delay to the work. Any claim for an
extensionoftimemustbenotiedinwritingtotheownerwithin10businessdays.
4. Variations to work
The work including materials may be varied by written agreement between the
owner and the contractor. A notice describing the variation, the cost of the additional
or omitted work and any change to the Completion Period must be provided to the
owner, and the notice must then be signed and dated by both parties to constitute
acceptance. The price of extra work, which includes GST, will be added to the
Contract Price. The cost of omitted work will be deducted from the Contract Price. If
thevariedcontractpriceexceeds$20,000,acerticateofinsuranceundertheHome
Building Compensation Fund must be attached to the contract and the additional
requirements for contracts over $20,000 must be included in this contract or a new
contract entered into that complies with the requirements in the Home Building Act
1989 for contracts over $20,000.
5. Insurance of work and personal injury
Before the contractor commences any work under this contract or is given access to
the site, the contractor must have current insurance cover for:
(a) public liability insurance to cover liabilities to third parties for death or
personal injury or damage to property for an amount not less than $5 million
(b) workers’ compensation insurance to cover any employees (if requested the
contractor must provide the owner with proof that all such insurances have been
taken out and are current), and
(c) property damage insurance for the work (including work in progress
and materials) for the full reinstatement and replacement cost.
6. Contractor’s indemnity in favour of owner
The contractor will indemnify the owner against any loss or liability for death, personal
injury or property damage arising out of the work under this contract, except to the
extent that the owner or, owner’s representative contributed to the loss or liability.
7. Damage to property
The contractor must make good any loss or damage to the work or property
of the owner caused by the contractor or the contractor’s employees, agents
or subcontractors. The owner must remove any furniture or personal goods
from the vicinity of the work to minimise the risk of damage.
8. Access for contractors
The owner must provide access for the contractor and any employee or
subcontractor of the contractor to carry out the work as required during work hours
allowed by relevant statutory authorities. The owner must remove any personal
property likely to impede the work.
9. Cleaning up
On completion of the work, the contractor must remove from the site all plant and
equipment and dispose of all rubbish, excavated material, vegetation, demolished
or dismantled structures and surplus material relating to the work. All demolished,
dismantled and surplus material will be the property of the contractor unless
otherwisespeciedinthedescriptionofwork.
10. Disputes
If the owner or contractor considers a dispute has arisen in relation to any matter
covered by this contract, that party must promptly give the other party written notice
of the items of dispute. If the dispute cannot be resolved the owner may notify Fair
Trading that a building dispute exists by either visiting www.fairtrading.nsw.gov.au
or ringing 13 32 20 and seek the assistance of NSW Fair Trading in resolving
the dispute.
11. Terminating contract
If the contractor becomes bankrupt or goes into liquidation, administration or is
otherwise without full capacity; fails to complete the work within the completion
period, or if no completion period is agreed, within a reasonable time; fails to remedy
defective work or replace faulty or unsuitable materials then the owner may, where
such default can be remedied, issue a written notice requiring the contractor to
remedy the default within 10 business days of receipt of the notice by the contractor
or within such other reasonable period as may be agreed. If the default is not
remedied within the 10 business days or other reasonable period as agreed, or is not
capable of being remedied, the owner may terminate the contract by written notice
to the contractor.
If the owner fails to make payment due under the contract or denies access
to the site to the contractor to prevent the work from proceeding, the contractor may
issue a written notice requiring the owner to remedy the default within 10 business
days of receipt of the notice by the owner. If the default is not remedied,
the contractor may terminate the contract by written notice to the owner.
12. Giving of notices
Any written notice required to be given under the contract or under the Home
Building Act 1989 may be served by:
(a) giving it to the party personally,
(b) leaving it at the party’s address shown in the contract, or
(c) sending it by registered post to the party’s address shown in the contract.
Contract conditions