Instructions for Completing Part 1
Part 1 is to be completed by the applicant or project sponsor. Responses become part of the application for approval or funding,
are subject to public review, and may be subject to further verification.
Complete Part 1 based on information currently available. If additional research or investigation would be needed to fully respond to
any item, please answer as thoroughly as possible based on current information; indicate whether missing information does not exist,
or is not reasonably available to the sponsor; and, when possible, generally describe work or studies which would be necessary to
update or fully develop that information.
Applicants/sponsors must complete all items in Sections A & B. In Sections C, D & E, most items contain an initial question that
must be answered either “Yes” or “No”. If the answer to the initial question is “Yes”, complete the sub-questions that follow. If the
answer to the initial question is “No”, proceed to the next question. Section F allows the project sponsor to identify and attach any
additional information. Section G requires the name and signature of the applicant or project sponsor to verify that the information
contained in Part 1is accurate and complete.
A. Project and Applicant/Sponsor Information.
Name of Action or Project:
Project Location (describe, and attach a general location map):
Brief Description of Proposed Action (include purpose or need):
Name of Applicant/Sponsor: Telephone:
E-Mail:
Address:
City/PO: State: Zip Code:
Project Contact (if not same as sponsor; give name and title/role): Telephone:
E-Mail:
Address:
City/PO: State: Zip Code:
Property Owner (if not same as sponsor): Telephone:
E-Mail:
Address:
City/PO: State: Zip Code:
FEAF 2019
Proposed Regional Recovery and Recycling Residue Facility (RRRF) Project Site at the Town of Brookhaven Solid Waste Management Facility (SWMF)
Town SWMF at 350 Horseblock Road in the hamlet of Yaphank, Town of Brookhaven, Suffolk County, New York 11719 (see Site Location Map)
Replace the Town of Brookhaven's existing combined 270-acre C&D and Ash landfill, containing approximately 215 acres of waste area, with a new
121-acre Regional Recovery and Recycling Residue Facility (RRRF) Project Site, containing an approximately 59-acre waste footprint. The proposed
facility will serve the Nassau-Suffolk region by accepting primarily ash residue generated by local Waste-To-Energy (WTE) plants, which serve as the
region's primary solid waste management system. See Attachment for greater detail.
Town of Brookhaven
(631) 451-8696
1 Independence Hill
Farmingville
New York
Christopher Andrade, Commissioner, Dept. Recycling & Sustainable Materials Management
(631) 451-8696
WasteManagement@brookhavenny.gov
1 Independence Hill
Farmingville
New York
11738
Page 2 of 13
B. Government Approvals
B. Government Approvals, Funding, or Sponsorship. (“Funding” includes grants, loans, tax relief, and any other forms of financial
assistance.)
Government Entity If Yes: Identify Agency and Approval(s)
Required
Application Date
(Actual or projected)
a. City Counsel, Town Board, 9 Yes 9 No
or Village Board of Trustees
b. City, Town or Village 9 Yes 9 No
Planning Board or Commission
c. City, Town or 9 Yes 9 No
Village Zoning Board of Appeals
d. Other local agencies 9 Yes 9 No
e. County agencies 9 Yes 9 No
f. Regional agencies 9 Yes 9 No
g. State agencies 9 Yes 9 No
h. Federal agencies 9 Yes 9 No
i. Coastal Resources.
i. Is the project site within a Coastal Area, or the waterfront area of a Designated Inland Waterway? 9 Yes 9 No
ii. Is the project site located in a community with an approved Local Waterfront Revitalization Program?
9 Yes 9 No
iii. Is the project site within a Coastal Erosion Hazard Area? 9 Yes 9 No
C. Planning and Zoning
C.1. Planning and zoning actions.
Will administrative or legislative adoption, or amendment of a plan, local law, ordinance, rule or regulation be the 9 Yes 9
N
o
only approval(s) which must be granted to enable the proposed action to proceed?
If Yes, complete sections C, F and G.
If No, proceed to question C.2 and complete all remaining sections and questions in Part 1
C.2. Adopted land use plans.
a. Do any municipally- adopted (city, town, village or county) comprehensive land use plan(s) include the site 9 Yes 9 No
where the proposed action would be located?
If Yes, does the comprehensive plan include specific recommendations for the site where the proposed action 9 Yes 9 No
would be located?
b. Is the site of the proposed action within any
local or regional special planning district (for example: Greenway;
9 Yes 9 No
Brownfield Opportunity Area (BOA); designated State or Federal heritage area; watershed management plan;
or other?)
If Yes, identify the plan(s):
_______________________________________________________________________________________________________
______________________________________________________________________________________________________
_
_
________________________________________________________________________________________________________
c. Is the proposed action located wholly or partially within an area listed in an adopted municipal open space plan, 9 Yes 9 No
or an adopted municipal farmland protection plan?
If Yes, identify the plan(s):
________________________________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
See Attachment
TBD
See Attachment
TBD
See Attachment
TBD
See Attachment
TBD
See Attachment
TBD
Beaver Dam Creek Watershed Management Plan (June 2009)
Page 3 of 13
C.3. Zoning
a. Is the site of the proposed action located in a municipality with an adopted zoning law or ordinance. 9 Yes 9 No
If Yes, what is the zoning classification(s) including any applicable overlay district?
_________________________________________________________________________________________________________
_________________________________________________________________________________________________________
b. Is the use permitted or allowed by a special or conditional use permit? 9 Yes 9 No
c. Is a zoning change requested as part of the proposed action? 9 Yes 9 No
If Yes,
i. What is the proposed new zoning for the site? ___________________________________________________________________
C.4. Existing community services.
a. In what school district is the project site located? ________________________________________________________________
b. What police or other public protection forces serve the project site?
_________________________________________________________________________________________________________
c. Which fire protection and emergency medical services serve the project site?
__________________________________________________________________________________________________________
d. What parks serve the project site?
__________________________________________________________________________________________________________
__________________________________________________________________________________________________________
D. Project Details
D.1. Proposed and Potential Development
a. What is the general nature of the proposed action (e.g., residential, industrial, commercial, recreational; if mixed, include all
components)?
_________________________________________________________________________________________________________
b. a. Total acreage of the site of the proposed action? _____________ acres
b. Total acreage to be physically disturbed? _____________ acres
c. Total acreage (project site and any contiguous properties) owned
or controlled by the applicant or project sponsor? _____________ acres
c. Is the proposed action an expansion of an existing project or use? 9 Yes 9 No
i. If Yes, what is the approximate percentage of the proposed expansion and identify the units (e.g., acres, miles, housing units,
square feet)? % ____________________ Units: ____________________
d. Is the proposed action a subdivision, or does it include a subdivision? 9 Yes 9 No
If Yes,
i. Purpose or type of subdivision? (e.g., residential, industrial, commercial; if mixed, specify types)
________________________________________________________________________________________________________
ii. Is a cluster/conservation layout proposed? 9 Yes 9 No
iii. Number of lots proposed? ________
iv. Minimum and maximum proposed lot sizes? Minimum __________ Maximum __________
9 Yes 9 No
_____ months
_____
_____ month _____ year
e. Will the proposed action be constructed in multiple phases?
i. If No, anticipated period of construction:
ii. If
Yes:
Total number of phases anticipated
Anticipated commencement date of phase 1 (including demolition)
Anticipated completion date of final phase
_____ month _____year
Generally describe connections or relationships among phases, including any contingencies where progress of one phase may
determine timing or duration of future phases: _______________________________________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
*
A Residence 1 District and L Industrial 1 of the Town of Brookhaven*
South Country Central School District
Suffolk County Police Department - 5th Precinct
Brookhaven Fire Department provides fire protection and Brookhaven Ambulance Company, Inc. d/b/a South Country Ambulance provides
emergency medical services to the subject property.
The subject property is an active solid waste management facility and does not place a demand on or utilize parks.
Municipal (proposed Regional Recovery and Recycling Residue Facility at the Town of Brookhaven Solid Waste Management Facility)
121±
93±
534±
**
**
**
**
**
*The proposed Regional RRRF Project Site would be located on Town of Brookhaven-owned property. The municipal use of the property within these
zoning districts is permitted by Section 85-894 of the Town Code. Such municipal use of the subject property was previously authorized by Town Board
resolution.
**The total number of phases required to "construct" the proposed facility will be determined during the final design of the project. Phasing will progress to
ensure that waste acceptance will not be interrupted, and will be based on actual waste acceptance rates.
**
Page 4 of 13
f. Does the project include new residential uses? 9 Yes 9 No
If Yes, show numbers of units proposed.
One
Family Two Family Three Family Multiple Family (four or more)
Initial Phase ___________ ___________ ____________ ________________________
At completion
of all phases ___________ ___________ ____________ ________________________
9 Yes 9 No g. Does the proposed action include new non-residential construction (including expansions)?
If Yes,
i. Total number of structures __2_________
ii. Dimensions (in feet) of largest proposed structure: ________height; ________width; and _______ length
iii. Approximate extent of building space to be heated or cooled: ______________________ square feet
h. Does the proposed action include construction or other activities that will result in the impoundment of any 9 Yes 9 No
liquids, such as creation of a water supply, reservoir, pond, lake, waste lagoon or other storage?
If Yes,
i. Purpose of the impoundment: ________________________________________________________________________________
ii. If a water impoundment, the principal source of the water: 9 Ground water 9 Surface water streams 9 Other specify:
_________________________________________________________________________________________________________
iii. If other than water, identify the type of impounded/contained liquids and their source.
_________________________________________________________________________________________________________
iv. Approximate size of the proposed impoundment. Volume: ____________ million gallons; surface area: ____________ acres
v. Dimensions of the proposed dam or impounding structure: ________ height; _______ length
vi. Construction method/materials for the proposed dam or impounding structure (e.g., earth fill, rock, wood, concrete):
________________________________________________________________________________________________________
D.2. Project Operations
a. Does the proposed action include any excavation, mining, or dredging, during construction, operations, or both? 9 Yes 9 No
(Not including general site preparation, grading or installation of utilities or foundations where all excavated
materials will remain onsite)
If Yes:
i .What is the purpose of the excavation or dredging? _______________________________________________________________
ii. How much material (including rock, earth, sediments, etc.) is proposed to be removed from the site?
Volume (specify tons or cubic yards): ____________________________________________
Over what duration of time? ____________________________________________________
iii. Describe nature and characteristics of materials to be excavated or dredged, and plans to use, manage or dispose of them.
________________________________________________________________________________________________________
________________________________________________________________________________________________________
iv. Will there be onsite dewatering or processing of excavated materials? 9 Yes 9 No
If yes, describe. ___________________________________________________________________________________________
________________________________________________________________________________________________________
v. What is the total area to be dredged or excavated? _____________________________________acres
vi. What is the maximum area to be worked at any one time? _______________________________ acres
vii. What would be the maximum depth of excavation or dredging? __________________________ feet
viii. Will the excavation require blasting? 9 Yes 9 No
ix. Summarize site reclamation goals and plan: _____________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
b. Would the proposed action cause or result in alteration of, increase or decrease in size of, or encroachment 9 Yes 9 No
into any existing wetland, waterbody, shoreline, beach or adjacent area?
If Yes:
i. Identify the wetland or waterbody which would be affected (by name, water index number, wetland map number or geographic
description): ______________________________________________________________________________________________
_________________________________________________________________________________________________________
(perimeter)
240±
1,700±
2,300±
N/A
Stormwater runoff control
Stormwater runoff
11.8±
15±
ft.
5,100± ft.
Stormwater impoundment areas (infiltration and pre-treatment basins) will be constructed via a combination of soil excavation and the placement and
compaction of excavated soils to form embankments.
Site Subgrade Preparation, Post-construction stormwater management facility
construction
0 (excavated soils are anticipated to be re-used on-site)
N/A
On-site soils are comprised primarily of sand and loam (see Item E.2.c on page 11) according to the USDA Soil Survey of Suffolk County, New
York. It is anticipated that excavated soils will be re-used on-site.
Excavated soils will be screened, sorted and stockpiled for construction and on-site operations.
74±
40±
Upon cessation of filling, the facility will follow closure standards that will comply with NYSDEC requirements applicable at the time of closure, and
the waste footprint will be reclaimed as future native grasslands/vegetated area.
Page 5 of 13
ii.
iii.
Describe how the proposed action would affect that waterbody or wetland, e.g. excavation, fill, placement of structures, or
alteration of channels, banks and shorelines. Indicate extent of activities, alterations and additions in square feet or acres:
_________________________________________________________________________________________________________
_________________________________________________________________________________________________________
_________________________________________________________________________________________________________
_________________________________________________________________________________________________________
Will the proposed action cause or result in disturbance to bottom sediments? Yes 9 No
If Yes, describe: __________________________________________________________________________________________
iv. Will the proposed action cause o
r result in the destruction or removal of aquatic vegetation?
9 Yes 9 No
If Yes:
acres of aquatic vegetation proposed to be removed: ___________________________________________________________
expected acreage of aquatic vegetation remaining after project completion:________________________________________
purpose of proposed removal (e.g. beach clearing, invasive species control, boat access): ____________________________
____________________________________________________________________________________________________
proposed method of plant removal: ________________________________________________________________________
if chemical/herbicide treatment will be used, specify product(s): _________________________________________________
v. Describe any proposed reclamation/mitigation following disturbance: _________________________________________________
_________________________________________________________________________________________________________
c. Will the proposed action use, or create a new demand for water? 9 Yes 9 No
If Yes:
i.
Total anticipated water usage/demand per day: __________________________ gallons/day
ii. Will the proposed action obtain water from an existing public water supply? 9 Yes 9 No
If Yes:
Name of district or service area: _________________________________________________________________________
Does the existing public water supply have capacity to serve the proposal? 9 Yes 9 No
Is the project site in the existing district? 9 Yes 9 No
Is expansion of the district needed? 9 Yes 9 No
Do existing lines serve the project site? 9 Yes 9 No
iii. Will line extension within an existing district be necessary to supply the project? 9 Yes 9 No
If Yes:
Describe extensions or capacity expansions proposed to serve this project: ________________________________________
____________________________________________________________________________________________________
Source(s) of supply for the district: ________________________________________________________________________
iv. Is a new water supply district or service area proposed to be formed to serve the project site? 9 Yes 9 No
If, Yes:
Applicant/sponsor for new district: ________________________________________________________________________
Date application submitted or anticipated: __________________________________________________________________
Proposed source(s) of supply for new district: _______________________________________________________________
v. If a public water supply will not be used, describe plans to provide water supply for the project: ___________________________
_________________________________________________________________________________________________________
vi. If water supply will be from wells (public or private), what is the maximum pumping capacity: _______ gallons/minute.
d. Will the proposed action generate liquid wastes? 9 Yes 9 No
If Yes:
i. Total anticipated liquid waste generation per day: _______________ gallons/day
ii. Nature of liquid wastes to be generated (e.g., sanitary wastewater, industrial; if combination, describe all components and
approximate volumes or proportions of each): __________________________________________________________________
_________________________________________________________________________________________________________
_________________________________________________________________________________________________________
iii. Will the proposed action use any existing public wastewater treatment facilities? 9 Yes 9 No
If Yes:
Name of wastewater treatment plant to be used: _____________________________________________________________
Name of district: ______________________________________________________________________________________
Does the existing wastewater treatment plant have capacity to serve the project? 9 Yes 9 No
Is the project site in the existing district? 9 Yes 9 No
Is expansion of the district needed? 9 Yes 9 No
*Water would be used for irrigation during the grow-in period for any plantings and for dust control, when necessary.
Water use is expected to be
minimal.
TBD*
Suffolk County Water Authority Distribution Area 12
A service line extension to the Project Site is anticipated to be required from the water main located at the existing Town Landfill.
Suffolk County Water Authority
50,000±
Liquid waste will be leachate generated from stormwater that comes in contact with residuals. Leachate will be conveyed to on-site storage tanks
and will be then be loaded onto trucks for disposal at the Bergen Point Wastewater Treatment Facility, in accordance with applicable regulations.
Suffolk Co. Southwest Sewer District No. 3, Bergen Point Wastewater Treatment Facility
Suffolk County Sewer District No. 3
9 Yes 9 No
Do existing sewer lines serve the project site?
Will a line extension within an existing district be necessary to serve the project?
9 Yes 9 No
If Yes:
Describe extensions or capacity expansions proposed to serve this project: ____________________________________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
iv. Will a new wastewater (sewage) treatment district be formed to serve the project site? 9 Yes 9 No
If Yes:
Applicant/sponsor for new district: ____________________________________________________________________
Date application submitted or anticipated: _______________________________________________________________
What is the receiving water for the wastewater discharge? __________________________________________________
v. If public facilities will not be used, describe plans to provide wastewater treatment for the project, including specifying proposed
receiving water (name and classification if surface discharge or describe subsurface disposal plans):
________________________________________________________________________________________________________
________________________________________________________________________________________________________
vi. Describe any plans or designs to capture, recycle or reuse liquid waste: _______________________________________________
________________________________________________________________________________________________________
_________________________________________________________
_
______________________________________________
e. Will the proposed action disturb more than one acre and create stormwater runoff, either from new point 9 Yes 9 No
sources (i.e. ditches, pipes, swales, curbs, gutters or other concentrated flows of stormwater) or non-point
source (i.e. sheet flow) during construction or post construction?
If Yes:
i.
How much impervious surface will the project create in relation to total size of project parcel?
_____ Square feet or _____ acres (impervious surface)
_____ Square feet or _____ acres (parcel size)
ii.
Describe types of new point sources. __________________________________________________________________________
_________________________________________________________________________________________________________
iii. Where will the stormwater runoff be directed (i.e. on-site stormwater management facility/structures, adjacent properties,
groundwater, on-site surface water or off-site surface waters)?
_
_______________________________________________________________________________________________________
________________________________________________________________________________________________________
If to surface waters, identify receiving water bodies or wetlands: ______________________________________
__________
____________________________________________________________________________________________________
____________________________________________________________________________________________________
Will stormwater runoff flow to adjacent properties? 9 Yes 9 No
iv. Does the proposed plan minimize impervious surfaces, use pervious materials or collect and re-use stormwater?
9 Yes 9 No
f. Does the proposed action include, or will it use on-site, one or more sources of air emissions, including fuel 9 Yes 9 No
combustion, waste incineration, or other processes or operations?
If Yes, identify:
i. Mobile sources during project operations (e.g., heavy equipment, fleet or delivery vehicles)
_________________________________________________________________________________________________________
ii. Stationary sources during construction (e.g., power generation, structural heating, batch plant, crushers)
______________________________________________________________________________________________________
__
iii. Stationary sources during operations (e.g., process emissions, large boilers, electric generation)
________________________________________________________________________________________________________
g. Will any air emission sources named in D.2.f (above), require a NY State Air Registration, Air Facility Permit, 9 Yes 9 No
or Federal Clean Air Act Title IV or Title V Permit?
If Yes:
i. Is the project site located in an Air quality non-attainment area? (Area routinely or periodically fails to meet 9 Yes 9 No
ambient air quality standards for all or some parts of the year)
ii. In addition to emissions as calculated in the application, the project will generate:
___________Tons/year (short tons) of Carbon Dioxide (CO
2
)
___________Tons/year (short tons) of Nitrous Oxide (N
2
O)
___________Tons/year (short tons) of Perfluorocarbons (PFCs)
___________Tons/year (short tons) of Sulfur Hexafluoride (SF
6
)
___________Tons/year (short tons) of Carbon Dioxide equivalent of Hydroflourocarbons (HFCs)
___________Tons/year (short tons) of Hazardous Air Pollutants (HAPs)
*Additionally, as noted on page 9 of 13, the waste footprint will be lined with an impervious membrane.
**The air emissions from the proposed filling operations will be a function of the quality and quantity of the exposed ash (as well as other inert
materials) over the course of the project. The emissions will be calculated once construction details are available. However, emissions of these
pollutants are anticipated to be de minimus
Page 6 of 13
The proposed Project Site will utilize a Leachate Collection System to collect stormwater that comes into contact with residuals and will convey
the liquid waste to on-site storage tanks in preparation for the loading of trucks for off-site disposal at the Suffolk County Southwest Sewer District
No. 3, Bergen Point Wastewater Treatment Facility.
8±*
534±
Interior, perimeter roadside channels and culverts will convey stormwater to on-site stormwater
management infrastructure. Impervious surfaces will sheet flow into roadside channels.
See ii, above.
Heavy earthwork equipment for construction and waste disposal, as well as waste disposal truck traffic into and out of the proposed RRRF Project Site.
During construction stationary sources will include screening operations for the screening of excavated soils.
**
**
**
**
**
**
Page 7 of 13
h. Will the proposed action generate or emit methane (including, but not limited to, sewage treatment plants, 9 Yes 9 No
landfills, composting facilities)?
If Yes:
i.
ii. Describe any methane capture, control or elimination measures included in project design (e.g., combustion to generate heat or
electricity, flaring): __
_____________
____________________________________________________________________________________________
i. Will the proposed action result in the release of air pollutants from open-air operations or processes, such as 9 Yes 9 No
quarry or landfill operations?
If Yes: Describe operations and nature of emissions (e.g., diesel exhaust, rock particulates/dust):
______________________________________________________________________________________________
j. Will the proposed action result in a substantial increase in traffic above present levels or generate substantial 9 Yes 9 No
new demand for transportation facilities or services?
If Yes:
i. When is the peak traffic expected (Check all that apply): Morni
ng Evening Weekend
Randomly between hours of __________ to ________.
ii. For commercial activities only, projected number of truck trips/day and type (e.g., semi trailers and dump trucks): _____________
iii.
iv.
v.
Parking spaces: Existing ___________________
Proposed ___________ Net increase/decrease _____________________
Does the proposed action include any shared use parking? Yes No
9 Yes 9 No
vi. Are public/private transportation service(s) or facilities available within ½ mile of the proposed site?
vii Will the proposed action include access to public transportation or accommodations for use
of hybrid, electric 9 Yes 9 No
or other alternative fueled vehicles?
viii
. W
ill the proposed action include plans for pedestrian or bicycle accommodations for connections to
existing 9 Yes
9 No
pede
strian or bicycle routes?
k. Will the proposed action (for commercial or industrial projects only) generate new or additional demand 9 Yes 9 No
for energy?
If Yes:
i. Estimate annual electricity demand during operation of the proposed action: ____________________________________________
_________________________________________________________________________________________________________
ii. A
nticipated sources/suppliers of electricity for the project (e.g., on-site combustion, on-site renewable, via grid/local utility, or
other):
_______________________________________________________________________________________________________
_
iii. Will the proposed action require a new, or an upgrade, to an existing substation?
9 Yes 9 No
l. Hours of operation. Answer all items which apply.
i. During Construction: ii. During Operations:
Monday - Friday: _________________________ Monday - Friday: ____________________________
Saturday: ________________________________ Saturday: ___________________________________
Sunday: _________________________________ Sunday: ____________________________________
Holidays: ________________________________ Holidays: ___________________________________
If the proposed action includes any modification of existing roads, creation of new roads or change in existing access, describe:
________________________________________________________________________________________________________
________________________________________________________________________________________________________
Estimate methane generation in tons/year (metric): _________________________________
There will be air emissions assoc. with the proposed facility; however, experience shows that emissions from such facilities are de minimus & below
regulatory limits for control systems. There is the potential for emissions from associated operations resulting from mobile equipment & truck traffic.
These emissions will be significantly less than what would be produced by truck traffic needed to move WTE ash residue off LI, absent the project.
Energy usage for the leachate pumps is estimated at approximately 100,000 kilowatt hours/year.*
Electric service to be provided via connection to existing grid (PSEG-LI) through underground primary electric cabling.
6:00 a.m. - 4:00 p.m.
6:00 a.m. - 4:00 p.m.
6:00 a.m. - 4:00 p.m.
Closed for Town Holidays
6:00 a.m. - 4:00 p.m.
6:00 a.m. - 4:00 p.m.
6:00 a.m. - 4:00 p.m.
Closed for Town Holidays
*However, for example, significantly more electricity is produced at the Covanta Hempstead Waste-to-Energy (WTE) Facility, from which most of the ash
residue is being transported. Covanta Hempstead produces 80 megawatts of electricity, 96% of which is available to the electric grid.
Page 8 of 13
m. Will the proposed action produce noise that will exceed existing ambient noise levels during construction, 9 Yes 9 No
operation, or both?
If yes:
i. Provide details including sources, time of day and duration:
_______________________________________________________________________________________________________
_______________________________________________________________________________________________________
ii. Will the proposed action remove existing natural barriers that could act as a noise barrier or screen?
9 Yes 9 No
Describe: _________________________________________________________________________________________________
_________________________________________________________________________________________________________
n. W thill prope os actioed havn e outd lighoor ting? 9 Yes 9 No
If yes:
i.
Describe source(s), location(s), height of fixture(s), direction/aim, and proximity to nearest occupied structures:
_________________________________________________________________________________________________________
_________________________________________________________________________________________________________
ii
.
Will proposed action remove existing natural barriers that could act as a light barrier or screen? 9 Yes 9 No
Describe: _________________________________________________________________________________________________
_________________________________________________________________________________________________________
o. Does the proposed action have the potential to produce odors for more than one hour per day? 9 Yes 9 No
If Yes, describe possible sources, potential frequency and duration of odor emissions, and proximity to nearest
occupied structures: ______________________________________________________________________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
p. 9 Yes 9 No Will the proposed action include any bulk storage of petroleum (combined capacity of over 1,100 gallons)
or chemical products 185 gallons in above ground storage or any amount in underground storage?
If Yes:
i. Product(s) to be stored ______________________________________________________________________________________
ii. Volume(s) ______ per unit time ___________
(e.g., month, year)
iii. Generally, describe the proposed storage facilities:________________________________________________________________
________________________________________________________________________________________________________
q. Will the proposed action (commercial, industrial and recreational projects only) use pesticides (i.e., herbicides, 9 Yes 9 No
insecticides) during construction or operation?
If Yes:
i.
Describe proposed treatment(s):
________________________________________________________________________________________________________
_______________________________________________________________________________________________________
_
________________________________________________________________________________________________________
________________________________________________________________________________________________________
ii. Will the proposed action use Integrated Pest Management Practices? 9 Yes 9 No
r. Will the proposed action (commercial or industrial projects only) involve or require the management or disposal 9 Yes 9 No
of solid waste (excluding hazardous materials)?
If Yes:
i. Describe any solid waste(s) to be generated during construction or operation of the facility:
Construction: ____________________ tons per ________________ (unit of time)
Operation : ____________________ tons per ________________ (unit of time)
ii.
Describe any proposals for on-site minimization, recycling or reuse of materials to avoid disposal as solid waste:
Construction: ________________________________________________________________________________________
____________________________________________________________________________________________________
Operation: __________________________________________________________________________________________
____________________________________________________________________________________________________
iii. Proposed disposal methods/facilities for solid waste generated on-site:
Construction: ________________________________________________________________________________________
____________________________________________________________________________________________________
Operation: __________________________________________________________________________________________
____________________________________________________________________________________________________
*
The construction and operation of the proposed facility will generate noise. However, the Applicant would comply with applicable noise regulations
per Chapter 50 of the Town of Brookhaven Town Code.
Existing forested areas on the subject property will be removed for the construction of the proposed RRRF. However, a min. 25 ft-foot-wide
vegetative buffer will be retained, leaving existing trees in place around the Project Site to provide a natural noise barrier and screen.
Proposed outdoor lighting will be provided at strategic locations along the proposed perimeter roadways. Fixtures are expected to be no taller than
15 feet. Lighting will be dark sky compliant, with no light spill beyond the property boundaries. Portable lights may be used at times.
An Odor Control Plan is being prepared as part of the NYSDEC SWMF Permit to provide assessments and mitigation measures for potential odor
releases from the operations at the proposed Regional RRRF.
*The proposed RRRF will be primarily a disposal area for ash residue, which is a WTE combustion process by-product. The majority of the ash residue will
come from the Covanta Hempstead WTE facility, where Town of Brookhaven MSW is taken for processing. The proposed Regional RRRF itself will not
generate solid waste; it will only generate leachate.
Page 9 of 13
9 Yes 9 No
i.
Type of management or handling of waste proposed for the site (e.g., recycling or transfer station, composting, landfill, or
other disposal activities): ___________________________________________________________________________________
t. Will the proposed action at the site involve the commercial generation, treatment, storage, or disposal of hazardous
9 Yes 9 No
waste?
If Yes:
i.
Name(s) of all hazardous wastes or constituents to be generated, handled or managed at facility: ___________________________
_________________________________________________________________________________________________________
_______________________________________________________________________________________________________
__
ii. Generally describe processes or activities involving hazardous wastes or constituents: ___________________________________
_________________________________________________________________________________________________________
________________________________________________________________________________________________________
iii. Specify amount to be handled or generated _____ tons/month
iv. Describe any proposals for on-site minimization, recycling or reuse of hazardous constituents: ____________________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
v. Will any hazardous wastes be disposed at an existing offsite hazardous waste facility? 9 Yes 9 No
If Yes: provide name and location of facility: _______________________________________________________________________
________________________________________________________________________________________________________
If No: describe proposed management of any hazardous wastes which will not be sent to a hazardous waste facility:
________________________________________________________________________________________________________
________________________________________________________________________________________________________
E. Site and Setting of Proposed Action
E.1. Land uses on and surrounding the project site
a. Existing land uses.
i. Check all uses that occur on, adjoining and near the project site.
9 Urban 9 Industrial 9 Commercial 9 Residential (suburban) 9 Rural (non-farm)
9 Forest 9 Agriculture 9 Aquatic 9 Other (specify): ____________________________________
ii. If mix of uses, generally describe:
__________________________________________________________________________________________________________
__________________________________________________________________________________________________________
b. Land uses and covertypes on the project site.
Land use or
Covertype
Current
Acreage
Acreage After
Project Completion
Change
(Acres +/-)
Roads, buildings, and other paved or impervious
surfaces
Forested
Meadows, grasslands or brushlands (non-
agricultural, including abandoned agricultural)
Agricultural
(includes active orchards, field, greenhouse etc.)
Surface water features
(lakes, ponds, streams, rivers, etc.)
Wetlands (freshwater or tidal)
Non-vegetated (bare rock, earth or fill)
Other
Describe: _______________________________
________________________________________
s. Does the proposed action include construction or modification of a solid waste management facility?
If Yes:
ii. Anticipated rate of disposal/processing:
________ Tons/month, if transfer or other non-combustion/thermal treatment, or
________ Tons/hour, if combustion or thermal treatment
iii. If landfill, anticipated site life: ________________________________
Landfill per 6 NYCRR Part 363-7.2; principal material to be received is WTE ash*
47,000±
To be determined
Municipal (Town of Brookhaven Solid Waste Management Facility)
The site is currently improved with various operations associated with the Town of Brookhaven Solid Waste Management Facility. The surrounding area is
currently improved with a mix of forested, residential, industrial, commercial and agricultural (horse farm) uses.
+7±
86±
23±
-63±
15±
+11±
0
0
0
0
0
0
0
29±
0
-29±
Proposed Waste Footprint**/Stormwater
Management Basin(s)
0
59±/15±
+59± /+15±
*6 NYCRR Part 363-7.2 allows disposal of residue from processes that separate, extract and recover usable materials, energy or heat from waste and
other inert materials. Environmental analyses to be performed will determine specific composition of materials to be landfilled. No MSW or Commercial
C&D will be accepted.
**The waste footprint will be lined with an impervious membrane.
Page 10 of 13
c. Is the project site presently used by members of the community for public recreation? 9 Yes 9 No
i. If Yes: explain: __________________________________________________________________________________________
d. Are there any facilities serving children, the elderly, people with disabilities (e.g., schools, hospitals, licensed 9 Yes 9 No
day care centers, or group homes) within 1500 feet of the project site?
If Yes,
i. Identify Facilities:
________________________________________________________________________________________________________
________________________________________________________________________________________________________
e. Does the project site contain an existing dam? 9 Yes 9 No
If Yes:
i. Dimensions of the dam and impoundment:
Dam height: _________________________________ feet
Dam length: _________________________________ feet
Surface area: _________________________________ acres
Volume impounded: _______________________________ gallons OR acre-feet
ii. Dam=s existing hazard classification: _________________________________________________________________________
iii. Provide date and summarize results of last inspection:
_______________________________________________________________________________________________________
_______________________________________________________________________________________________________
f. Has the project site ever been used as a municipal, commercial or industrial solid waste management facility, 9 Yes 9 No
or does the project site adjoin property which is now, or was at one time, used as a solid waste management facility?
If Yes:
i. Has the facility been formally closed? 9 Yes 9 No
If yes, cite sources/documentation: _______________________________________________________________________
ii. Describe the location of the project site relative to the boundaries of the solid waste management facility:
________________________________________________________________________________________________________
_ _______________________________________________________________________________________________________
iii. Describe any development constraints due to the prior solid waste activities: __________________________________________
_______________________________________________________________________________________________________
g. Have hazardous wastes been generated, treated and/or disposed of at the site, or does the project site adjoin 9 Yes 9 No
property which is now or was at one time used to commercially treat, store and/or dispose of hazardous waste?
If Yes:
i. Describe waste(s) handled and waste management activities, including approximate time when activities occurred:
_______________________________________________________________________________________________________
_______________________________________________________________________________________________________
h. Potential contamination history. Has there been a reported spill at the proposed project site, or have any 9 Yes 9 No
remedial actions been conducted at or adjacent to the proposed site?
If Yes:
i. Is any portion of the site listed on the NYSDEC Spills Incidents database or Environmental Site 9 Yes 9 No
Remediation database? Check all that apply:
9 Yes – Spills Incidents database Provide DEC ID number(s): ________________________________
9 Yes – Environmental Site Remediation database Provide DEC ID number(s): ________________________________
9 Neither database
ii. If site has been subject of RCRA corrective activities, describe control measures:_______________________________________
________________________________________________________________________________________________________
_
_______________________________________________________________________________________________________
iii. Is the project within 2000 feet of any site in the NYSDEC Environmental Site Remediation database? 9 Yes 9 No If
yes, provide DEC ID
number(s): ____________________________________________________________________________
iv. If yes to (i), (ii) or (iii) above, describe current status of site(s):
_______________________________________________________________________________________________________
_______________________________________________________________________________________________________
*
*
*The proposed Regional RRRF Project Site has been used for over 20 years for the storage and processing of natural materials in support of
separately permitted waste management activities occurring elsewhere within the overall 534±-acre SWMF. Five out of the six cells at the adjacent
landfill at the the Brookhaven SWMF have been closed and capped. Cell 6 is anticipated to reach capacity in 2024, simultaneous with the opening
of the Regional RRRF.
The proposed action involves the creation of a 59±-acre waste footprint within a 121-acre Regional RRRF Project Site situated within the
boundaries of the Town of Brookhaven Solid Waste Management Facility.
N/A
The only hazardous waste received at the Town SWMF (not the RRRF Project Site) is from Town residents using the Household Hazardous Waste
Facility. This material is temporarily stored on-site at the SWMF before being disposed off-site in accordance with relevant prevailing regulations.
See Attachment
152041
N/A
152041
See Attachment
Page 11 of 13
v. Is the project site subject to an institutional control limiting property uses? 9 Yes 9 No
If yes, DEC site ID number: ____________________________________________________________________________
Describe the type of institutional control (e.g., deed restriction or easement): ____________________________________
Describe any use limitations: ___________________________________________________________________________
Describe any engineering controls: _______________________________________________________________________
Will the project affect the institutional or engineering controls in place? 9 Yes 9 No
Explain: ____________________________________________________________________________________________
___________________________________________________________________________________________________
___________________________________________________________________________________________________
E.2. Natural Resources On or Near Project Site
a. What is the average depth to bedrock on the project site? ________________ feet below grade surface (bgs)
b. Are there bedrock outcroppings on the project site? 9 Yes 9 No
If Yes, what proportion of the site is comprised of bedrock outcroppings? __________________%
c. Predominant soil type(s) present on project site:
___________________________
__________%
____________
_______________ __________%
____________________________
__________%
d. What is the average depth to the water table on the project site? Average: _________ feet
e. Drainage status of project site soils: 9 Well Drained: _____% of site
9 Moderately Well Drained: _____% of site
9 Poorly Drained
_____%
of site
f. Approximate proportion of proposed action site with slopes: 9 0-10%: _____% of site
9 10-15%: _____% of site
9 15% or greater: _____% of site
g. Are there any unique geologic features on the project site? 9 Yes 9 No
If Yes, describe: _____________________________________________________________________________________________
________________________________________________________________________________________________________
h. Surface water features.
i. Does any portion of the project site contain wetlands or other waterbodies (including streams, rivers, 9 Yes 9 No
ponds or lakes)?
ii. Do any wetlands or other waterbodies adjoin the project site? 9 Yes 9 No
If Yes to either i or ii, continue. If No, skip to E.2.i.
iii. Are any of the wetlands or waterbodies within or adjoining the project site regulated by any federal, 9 Yes 9 No
state or local agency?
iv. For each identified regulated wetland and waterbody on the project site, provide the following information:
Streams: Name ____________________________________________ Classification _______________________
Lakes or Ponds: Name ____________________________________________ Classification _______________________
Wetlands:
Name ____________________________________________ Approximate Size ___________________
Wetland No. (if regulated by DEC) _____________________________
v. Are any of the above water bodies listed in the most recent compilation of NYS water quality-impaired 9 Yes 9 No
waterbodies?
If yes, name of impaired water body/bodies and basis for listing as impaired: _____________________________________________
___________________________________________________________________________________________________________
i. Is the project site in a designated Floo dway?
9 Yes 9 No
j. Is the project site in the 100-year Floodplain?
9 Yes 9 No
k. Is the project site in the 500-year Floodplain?
9 Yes 9 No
l. Is the project site located over, or immediately adjoining, a primary, principal or sole source aquifer? 9 Yes 9 No
If Yes:
i. Name of aquifer: _________________________________________________________________________________________
__ ________%
1,600±
(CpA) Carver and Plymouth sands, 0 to 3 percent slopes
11±
(HaA) Haven loam, 0 to 2 percent slopes
39±
(RdA) Riverhead sandy loam, 0 to 3 percent slopes
43±
(RdB) Riverhead sandly loam, 3 to 8 percent slopes
10-15
100
100
Regulated Freshwater Wetland (Beaverdam Creek)
157.3 (on- and off-site)
B-5
Beaverdam Creek is a 303(d) impaired water body that does not meet water quality standards as a result of increased concentrations of Ammonia.
Nassau-Suffolk Sole Source Aquifer
Page 12 of 13
m. Identify the predominant wildlife species that occupy or use the project site: ______________________________
______________________________ _______________________________ ______________________________
______________________________ ____________________________
___ ______________________________
n. Does the project site contain a designated significant natural community? 9 Yes 9 No
If Yes:
i.
Describe the habitat/community (composition, function, and basis for designation): _____________________________________
________________________________________________________________________________________________________
ii. Source(s) of description or evaluation: ________________________________________________________________________
iii. Ex
tent of community/habitat:
Curren
tly: ______________________ acres
Following completion of project as proposed: _____________________ acres
Gain or loss (indicate + or -): ______________________ acres
o. Does project site contain any species of plant or animal that is listed by the federal government or NYS as 9 Yes 9 No
endangered or threatened, or does it contain any areas identified as habitat for an endangered or threatened species?
p. Does the project site contain any species of plant or animal that is listed by NYS as rare, or as a species of 9 Yes 9 No
special concern?
q. Is the project site or adjoining area currently used for hunting, trapping, fishing or shell fishing? 9 Yes 9 No
If yes, give a brief description of how the proposed action may affect that use: ___________________________________________
________________________________________________________________________________________________________
E.3. Designated Public Resources On or Near Project Site
a. Is the project site, or any portion of it, located in a designated agricultural district certified pursuant to 9 Yes 9 No
Agriculture and Markets Law, Article 25-AA, Section 303 and 304?
If Yes, provide county plus district name/number: _________________________________________________________________
b. Are agricultural lands consisting of highly productive soils present? 9 Yes 9 No
i. If Yes: acreage(s) on project site? ___________________________________________________________________________
ii. Source(s) of soil rating(s): _________________________________________________________________________________
c. Does the project site contain all or part of, or is it substantially contiguous to, a registered National 9 Yes 9 No
Natural Landmark?
If Yes:
i. Nature of the natural landmark: 9 Biological Community 9 Geological Feature
ii. Provide brief description of landmark, including values behind designation and approximate size/extent: ___________________
________________________________________________________________________________________________________
________________________________________________________________________________________________________
d. Is the project site located in or does it adjoin a state listed Critical Environmental Area? 9 Yes 9 No
If Yes:
i. CEA name: _____________________________________________________________________________________________
ii. Basis for designation: _____________________________________________________________________________________
iii. Designating agency and date: ______________________________________________________________________________
If Yes:
i. Species and listing (endangered or threatened):______________________________________________________________________________
_
___________________________________________________________________
____________________________________________________
________________________________________________________________________________________________________________________
If Yes:
i. Species and listing:____________________________________________________________________________________________________
_______________________________________________________________________________________________________________________
**
Herring gull (Larus argentatus)
whitetail deer (Odocoileus virginianus)
black-capped chickadee (Poecile atricapillus)
raccoon (Procyon lotor)
blue jay (Cyanocitta cristata)
eastern chipmunk (Tamias striatus)*
*List is not exhaustive, and, at this time, is based on published data of most common species.
**Based on a review of the New York State Department of Environmental Conservation's (NYSDEC) Environmental Resource Mapper (accessed February
2020), the subject property is located in the vicinity of the Northern Long-eared bat listed as endangered or threatened in New York State. Consultation will
be initiated with the New York Natural Heritage Program.
Page 13 of 13
e. Does the project site contain, or is it substantially contiguous to, a building, archaeological site, or district 9 Yes 9 No
which is listed on the National or State Register of Historic Places, or that has been determined by the Commissioner of the NYS
Office of Parks, Recreation and Historic Preservation to be eligible for listing on the State Register of Historic Places?
If Yes:
i. Nature of historic/archaeological resource: 9 Archaeological Site 9 Historic Building or District
ii. Name: _________________________________________________________________________________________________
iii. Brief description of attributes on which listing is based:
_______________________________________________________________________________________________________
f. Is the project site, or any portion of it, located in or adjacent to an area designated as sensitive for 9 Yes 9 No
archaeological sites on the NY State Historic Preservation Office (SHPO) archaeological site inventory?
g. Have additional archaeological or historic site(s) or resources been identified on the project site? 9 Yes 9 No
If Yes:
i. Describe possible resource(s): _______________________________________________________________________________
ii. Basis for identification: ___________________________________________________________________________________
h. 9 Yes 9 No
Is the project site within fives miles of any officially designated and publicly accessible federal, state, or local
scenic or aesthetic resource?
If Yes:
i. Identify resource: _________________________________________________________________________________________
ii. Nature of, or basis for, designation (e.g., established highway overlook, state or local park, state historic trail or scenic byway,
etc.): ___________________________________________________________________________________________________
iii. Distance between project and resource: _____________________ miles.
i. Is the project site located within a designated river corridor under the Wild, Scenic and Recreational Rivers 9 Yes 9 No
Program 6 NYCRR 666?
If Yes:
i. Identify the name of the river and its designation: ________________________________________________________________
ii. Is the activity consistent with development restrictions contained in 6NYCRR Part 666? 9 Yes 9 No
F. Additional Information
Attach any additional information which may be needed to clarify your project.
If you have identified any adverse impacts which could be associated with your proposal, please describe those impacts plus any
measures which you propose to avoid or minimize them.
G. Verification
I certify that the information provided is true to the best of my knowledge.
Applicant/Sponsor Name ___________________________________ Date_______________________________________
Signature________________________________________________ Title_______________________________________
*
Wertheim National Wildlife Refuge; Carmans River
National Wildlife Refuge; Wild, Scenic and Recreational River
0.75±; 1.0 - 1.5±
VHB on behalf of the Town of Brookhaven
July 20, 2020
PRINT FORM
Senior Project Manager
*Because the project site is located in an archaeologically sensitive area and because New York State Department of Environmental Conservation
(NYSDEC) approval will be needed for the SWPPP, a Project Notification would be submitted to the Office of Parks, Recreation, and Historic
Preservation (OPRHP) to initiate review of the impacts to potential archaeological resources (if present) in accordance with Section 14.09 of the
State Historic Preservation Act. Upon receipt of the Project Notification, the OPRHP may request additional information to inform its review, such
as a Phase I Archaeological Survey.