DEMOLITION PERMIT 20150612
CITY OF AUBREY
107 S. Main St.
Aubrey, Texas 76227
940-440-9343
DEMOLITION PERMIT
In Accordance with City Ordinances #278-99, #371-06, and #470-12
Date Issued: ________________________ Date Expires: ______________________
Applicant Name: _________________________________________________________
Applicant Address: ________________________________________________________
Phone Number:___________________________________________________________
Property Owner: __________________________________________________________
Construction Address: _____________________________________________________
Disposal Method: _________________________________________________________
The City of Aubrey authorizes _____________________________________________________
to demolish or otherwise remove the existing structure as pictured. The structure will be moved
at the owner’s sole cost and expense. It is the owner’s responsibility to completely clear and
remove therefrom all materials, fixtures, garbage, refuge and debris. The owner’s must take all
responsibility for any accidents or incidents that may occur, and all liabilities for damages,
claims, of any nature arising out of or connected to the removal of said structure. The work of
demolishing any building shall not commence until the required pedestrian protection structures
are in place. The Code Enforcement Officer may require the requestor to submit plans and a
complete schedule for demolition. Where such are required, no work shall be done until such
plans or schedule, or both, are approved by the Mayor and Code Enforcement Officer. PLEASE
NOTE: All State guidelines for permitting and reporting of asbestos must be followed.
PHOTO of described property must be submitted.
Demolition must be completed within sixty (60) days from date of issuance.
Demolition Permit Fee $150.00
Initial Inspection Fee $ 55.00
Final Inspection Fee $ 55.00
DEMOLITION FEE: __________ ___________________________________
o Cash Applicant Signature Date
o Check # _________
RECEIPT # ________________
________________________________ ____________________________________
Approval-Public Works Date Approval-Mayor Date
INITIAL INSPECTION FINAL INSPECTION
APPROVED BY: APPROVED BY: