2.18
Power source location and the type of service coordinated with utility
company.
2.19
Power source pole number shown.
2.20
Service disconnect and meter placed 10' or less from the power source.
2.21
Additional service disconnect provided where the pedestal meter is
across the roadway or where the cabinet is located more than 50' from
the power source.
2.22
Standard controller cabinet placed with the door facing away from the
road.
2.23
Lighting system properly grounded.
2.24
Controller cabinet placement permits safe access. Cabinet is protected,
if needed.
2.25
Correct cabinet size used based on the number of light fixtures needed.
2.26
Cabinet base extension provided for Type P/R and Type M cabinets.
2.27
No utility lighting proposed.
2.28
Appropriate lighting poles used.
2.29
Appropriate davit arm length used.
2.30
Appropriate foundations used.
2.31
Lighting equipment placed outside of clear zone, if possible.
2.32
Junction wells, conduit and wires are the correct size and type.
2.33
Sole source items used for lighting projects in Kent County and Sussex
County.
2.34
Conduit fill capacity checked.
2.35
Lighting service schedule filled out correctly.
2.36
Lighting standard schedule filled out correctly.
2.37
Equipment locations do not affect maintenance activities.
2.38
Underground utility conflicts avoided.
2.39
Overhead utility conflicts avoided.
2.40
All details for special equipment provided.
2.41
Cover sheet provided. (May not be needed for smaller projects)
2.42
Index sheet provided. (May not be needed for smaller projects)
2.43
Project notes sheet provided. (Separate project notes sheet may not be
needed for smaller projects)
2.44
Lighting details sheet provided.
2.45
Voltage drop calculations checked and provided.
2.46
Correct wire size used based on the circuit layout.