DEMOLITION
INFORMATION
PERMIT REQUIRED
A demolition permit is required from any person desiring to demolish a structure.
The following conditions and requirements apply:
• If the structure is located in an area having a Homeowner’s Association, the
property owner is obligated to check with the Homeowner’s Association to
ensure compliance with their regulations.
• Allowable hours for construction within the Village are 6:30 a.m. to 8:30 p.m.
daily.
• Demolitions are authorized on a case-by-case basis.
APPLICATION CHECKLIST
All applications for a demolition permit shall include the following items and information:
o a completed short-form permit application listing the contractor(s) performing the work;
o valid contractor registration with the Village of Sugar Grove;
o a copy of the contract with the property owner’s signature; and
o disconnection approval letters from each utility.
CONTRACTOR REGISTRATION
Any contractor engaged in or having obligation to do work where the scope of work requires a
building permit is required to be registered with the Village of Sugar Grove. If the contractor is
not currently registered with the Village, a registration application can be obtained from the
Building Division at 630.391.7220 or from the Village’s website www.sugargroveil.gov
INSPECTIONS REQUIRED
Inspections may include: the open hole prior to backfilling and a final after restoration
depending on the scope of construction. The owner/contractor is responsible for scheduling all
required inspections. Please call 630.391.7220 to schedule the inspections. Please schedule the
inspections by 3:30 PM THE DAY BEFORE you want it.
PLAN REVIEW
Please allow 10 (ten) working days for processing.
PERMIT FEE
Structure without utility connections or plumbing $155.00
Structure with utility connections or plumbing $265.00
Additional fees may be charged if there is a grade change proposed or the proposed
modification requires review and inspection by the Village Engineer.