City of Rosenberg
INITIAL INFRASTRUCTURE APPLICATION
PLAN REVIEW SUBMITTAL
2220 4
th
Street, Rosenberg, Texas 77471
Telephone: 832-595-3500 Fax: 832-595-3501
www.rosenbergtx.gov
Rev. 02-19-19 DA
Date Received: Received By: Permit Number:
Plan Review Fee required at time of submittal
(Please refer to the attached fee schedule)
Project Address: Project Valuation:
$
Project Title:
Plat Approved
YES **
NO
** No permit will be issued until the plat is approved
Contact Person: Business Phone:
Business Fax: Email:
Engineer: Company Name: Business Phone:
Describe Proposed Construction (Water, Sewer, Paving, Storm-sewer, etc.):
SIGNATURE OF ENGINEER
REVISED SUBMITTALS WILL NOT BE
ACCEPTED WITHOUT RED-LINES BEING
RETURNED
***********************THERE WILL BE NO REFUND OR TRANSFER OF FEES*******************
City of Rosenberg
INITIAL INFRASTRUCTURE APPLICATION
2220 4
th
Street, Rosenberg, Texas 77471
Telephone: 832-595-3500 Fax: 832-595-3501
www.rosenbergtx.gov
Rev. 02-19-19 DA
Infrastructure Project Checklist/Information
Upon submittal of the Initial Infrastructure Application
the following must be submitted:
Two (2) sets of plans
One (1) set of plans in an electronic format
Plan review fee (reference fee schedule
attached to application)
Please allow at least 10-15 business days for review of
your plans
Once plans have been approved, a Pre-Construction
Meeting will need to be scheduled by contacting Debbi
Eben at Jones|Carter (281-762-6531). The Contractor
as well as the Engineer should be present at this
meeting.
Prior to the issuance of the Contractor’s Permit, the
following must be submitted:
Spec Books & Plans - 3 CD’s (PDF Format)
4 full size sets of signed plans (5, if Capital
Improvement Project)
4 half size sets of signed plans
3 Copies of Pre-Con sign in list
2 Copies of NTP (Notice to Proceed)
Copy of Executed Agreement (between Owner
and Contractor) with Contract Amount
□ If the project is disturbing one acre of land or more
(within the City Limits) you will be required to apply for
a Land Disturbance Permit. In order to apply, the
following MUST be received by the permit office:
Proof of filing Notice of Intent with the State
(through TCEQ)
Complete, BOUND copy of the SWPPP (Storm
Water Pollution Prevention Plan)
□ Once project is completed, the following must be
submitted:
As-Built/Record Plans - 2 Full Size
As-Built/Record Plans - 2 Half Size
As-Built/Record Plans – 3 CD’s (PDF & *GIS
Data or CAD Format; See Provided Details)
Final Inspection Letter from Engineer
Signature: Date:
City of Rosenberg
INFRASTRUCTURE
SUBMITTAL FEE SCHEDULE
2220 4
th
Street, Rosenberg, Texas 77471
Telephone: 832-595-3500 Fax: 832-595-3501
Rev. 02-19-19 - DA
I hereby certify I have read and examined this document and know the same to be true and correct. All provisions of law
and ordinances governing this type of work will be complied with whether specified herein or not. I further understand that
plans submitted for approval will be subjected to a comprehensive check against municipal ordinance and building code.
Any set of plans that must be returned for modifications or corrections in order to come into compliance with ordinance or
code will be subject to rechecking in order of submittal. Under no circumstances will paid fees be refunded or transferred.
Applications and plans will be held for 90 days. After 90 days this application and plans will be disposed of unless a valid
INFRASTRUCTURE building permit is issued.
Signature of Contractor or Authorized Agent Date
FEE SCHEDULE
PLAN REVIEW FEE __________________________________________________________
Plan Review Fee shall be as follows:
a. One percent (1%) of the actual construction cost for projects fifty thousand dollars ($50,000.00) or less, or
b. Five hundred dollars for the first $50,000.00 plus one-half percent (0.5%) of the actual construction cost over
$50,000.00
Total Valuation
Fee
$50,000.00 and less
One percent (1%) of the actual construction cost of the project.
$50,000.01 and up
$500 for the first $50,000.00 plus one-half percent (0.5%) of the actual construction cost
over $50,000.00.
EXAMPLE
INITIAL PLAN REVIEW FEE
VALUATION…………………….. $100,000.00
1
st
$50,000 ………………………………………………... + $500.00
Balance: $50,000 x 0.005 ...……..….………………..…+ $250.00
TOTAL: …………………………………………………………………………..= $750.00
INFRASTRUCTURE PERMIT FEE ___________________________________________________________
Inspection fee for water, sanitary sewer, drainage, and street improvements. Applicant shall provide estimated costs, and
supporting information for determination of the cost of the project. These fees shall be payable on the earlier of the time of
platting or upon request for an infrastructure permit. The fee shall be one percent (1%) of the actual construction cost
of the project.
INFRASTRUCTURE PERMIT FEE (Construction Portion)
VALUATION…………………….. $100,000.00
$100,000 x .01 …….………………………………………………………………………= $1,000.00
click to sign
signature
click to edit