APPLICATION CHECKLIST
All applications for a curb modification permit shall include the following items and information:
o a completed short-form permit application listing the contractor(s) performing the work.
o a certificate of insurance from the contractor listing the Village of Sugar Grove as an
additional insured
o valid contractor registration with the Village of Sugar Grove
o a cash security bond in the amount of $1,000. The surety is intended to ensure the
restoration of any disturbed areas and any damage to Village roadways and facilities
caused by or resulting from operations connected with the curb modification authorized
by the permit. Assuming the construction area is satisfactorily restored and there is no
damage to the street, the security bond will be returned to the applicant.
CONTRACTOR REGISTRATION
Any contractor engaged in or having obligation to do work where the scope of work requires a
building permit is required to be registered with the Village of Sugar Grove. If the contractor is
not currently registered with the Village, a registration application can be obtained from the
Building Division at 630.391.7220 or from the Village’s website www.sugargroveil.gov
INSPECTIONS REQUIRED
Prior to issuing the permit, an initial site inspection to assess the impact of the curb modification
on surface drainage and to document existing conditions will be performed. Once a curb
modification permit is issued, a pre-pour and a final inspection after pouring are required. The
owner/contractor is responsible for scheduling all required inspections. Please call 630.391.7220
to schedule the inspections. Please schedule the inspections by 3:30 PM THE DAY BEFORE you
want it.
PLAN REVIEW
Please allow 10 (ten) working days for processing.
PERMIT FEE
Curb modification, including the driveway apron $ 95.00, plus $1,000 right-of-
way damage and restoration
security guarantee
Curb modification, with driveway and /or public walk $185.00, plus $1,000 right-of-
way damage and restoration
security guarantee
Additional fees may be charged if there is a grade change proposed or the proposed
modification requires review and inspection by the Village Engineer.
The permit fee is paid when the permit is picked-up after the application has been reviewed and
approved.
NO WORK CAN BEGIN UNTIL THE PERMIT HAS BEEN ISSUED. WORK BEGUN PRIOR TO
ISSUANCE OF THE PERMIT WILL INCUR A FINE, PENALTY OR BOTH.