ARTS POLICY COMMITTEE MEETING
March 7, 2019
SCDOT Project Update
1. 0034300 - SC 125 (East Buena Vista Avenue/Atomic Road) Corridor Improvement –ARTS
• Current Budget - $800,000 P
E, $2,527,000 ROW, $38,000 UTIL, $8,694,172.58 CONST
• Construction is now complete, w
ith the final inspection was held Monday, October 15, 2018
• Contractor has completed all punch list ite
ms
2. 0034292 - S
C 302 (Silver Bluff Road) Corridor Improvement – Aiken County - ARTS
• Current Budget - $920,000 P
E, $1,700,000 R/W, $73,781 UTIL, $6,198,935.63 CONST
• Improvements include widening corridor to 3 lanes, addition of
turn lanes, curb and gutter
and signalization of three intersections
• Construction P
hase is currently underway (work began on March 29, 2016)
• SCDOT a
nd Eagle Construction have negotiated a new construction completion date of July
31, 2019.
• To a
ccelerate construction, and reduce impacts to the traveling public, SCDOT is offering
i
ncentives to the contractor to potentially finish up to 120 days before July 31.
3. 0041446 - SC 126 (Belvedere-Clearwater Road) Widening - ARTS
• Current Budget - $1,300,000 P
E, $2,139,600 ROW, $12,000,000 CONST
• Preliminary Engineering Phase has been completed, including Environmental Studies a
nd
F
inal Right-of-Way Plans
• Environmental Document/Public Hearing Certification was approved on
April 26, 2016
• Environmental Permitting Coordination i
s currently underway
• Right-of-W
ay Phase is underway (86 tracts) -- Right-of-Way Consultant (PRIMACQ) is in
the process of securing right of way for the project (83 tracts secured).
• Current S
chedule
o Construction O
bligation – 12/2019
o Letting – 02/
2020
4. 0040695 - S
C 118 (Hitchcock Parkway) Corridor Improvement - ARTS
• Current Budget – $3,300,
000 PE (per obligation from widening carried over), $1,496,800
R
OW, $12,200,000 CONST (Federal Resurfacing fund to pay for resurfacing of Hitchcoc
k
P
arkway)
• Right-of-W
ay obligated in December 2018 with initial property owner contact beginning
Quarter 1 of 2019.
• Current S
chedule
o Construction O
bligation – 4/2020
o Letting – 6/
2020
5. P037361 – S
C 19 (Whiskey Road)Intersection with Eagle Road and S-447 (Old Whiskey
Road) - ARTS
• Current Budget - $450,000 P
E, $400,000 ROW, $1,250,000
• Surveys a
nd traffic study have been completed.
• SCDOT i
s currently negotiating a contract with Parrish and Partners to provide design
s
ervices, Consultant working under a Limited Notice to Proceed to begin plan development
while contract negotiations are finalized.
• Current S
chedule
o Right o
f Way – Q3 2019
o Construction – Q1 2021
P
age 1 of 1